1
|
21st January 2015
|
- Discussion of project proposal & objectives
|
Supervisor Meeting 1 Minutes
|
|
2
|
12th February 2015
|
NOTE: CHANGE OF SUPERVISOR
- Explanation of current project to Dr Kam
- Present motivation, objectives and approaches
- Discussed proposal
|
Supervisor Meeting 2 Minutes
|
|
3
|
17th February 2015
|
- Proposal of new project scope based on discussion with sponsors
- Gather feedback on improvements
|
Supervisor Meeting 3 Minutes
|
|
4
|
24th February 2015
|
NOTE: Change of dataset!
- Discussion of new project scope
- Discussion of potential approaches
|
Supervisor Meeting 4 Minutes
|
|
5
|
5th March 2015
|
- Consult Dr Kam about our new approaches
- Discussion of suitable statistical analysis
- Consult Dr Kam regarding the building of a model
|
Supervisor Meeting 5 Minutes
|
|
6
|
12th March 2015
|
- Update of current progress and findings
|
Supervisor Meeting 6 Minutes
|
|
7
|
19th March 2015
|
- Update of current progress and findings
|
Supervisor Meeting 7 Minutes
|
|
8
|
2nd April 2015
|
- Update of current progress and findings
|
Supervisor Meeting 8 Minutes
|
|
9
|
11th April 2015
|
- Update of current progress and findings
- Consult Dr Kam on building on explanatory model
|