Maxco Project Development Status

From IS480
Jump to navigation Jump to search

Maxco Project Development Status

Iteration 1 - Inception Phase

Task Modules Involved Status Expected date of completion Actual date of completion Day Overdue
1 Project Management & Planning
Define main roles & responsibilities Completed 1st July 2010 1st July 2010 0
Set team expectations & goals Completed 1st July 2010 1st July 2010 0
Risk management plan Completed 2nd July 2010 2nd July 2010 0
Define Metrics Completed 2nd July 2010 2nd July 2010 0
Define rough project schedule Completed 2nd July 2010 2nd July 2010 0
2 Requirements
Understand and discuss project functional/non-functional requirements Completed 3rd July 2010 3rd July 2010 0
Project vision Completed 3rd July 2010 3rd July 2010 0
Technology Exploration 1 (Adobe Flex/Facebook) Completed 3rd July 2010 3rd July 2010 0
Update wiki page check Completed 3rd July 2010 3rd July 2010 0
3 Project Management
Milestone: Project Proposal Completed 7th July 2010 7th July 2010 0
Milestone: End of Inception Phase Completed 7th July 2010 7th July 2010 0

Iteration 2 - Elaboration 1 Phase

Task Modules Involved Status Expected date of completion Actual date of completion Day Overdue
1 Business Modeling
Class Diagram Completed 9th July 2010 9th July 2010 0
2 Requirements
Technology Exploration 2 (Adobe Flex/Facebook) Completed 15th July 2010 13th July 2010 -2
ER Diagram / Database Logical Diagram Completed 11th July 2010 10th July 2010 -1
Update wiki page check Completed 11th July 2010 11th July 2010 0
3 Implementation
B1G1 World Facebook application
Database Connectivity Completed 16th July 2010 16th July 2010 0
Facebook App Permissions for Wall post/Information Completed 18th July 2010 18th July 2010 0
Syncing Facebook and B1G1 account Completed 22nd July 2010 21nd July 2010 -1
B1G1 World
Database Connectivity Completed 17th July 2010 17th July 2010 0
Google map implementation Completed 17th July 2010 17th July 2010 0
Geocoding for latitude/longtitude of address Completed 19th July 2010 19th July 2010 0
Plotting of entities on map Completed 20th July 2010 20th July 2010 0
Animation framework for displaying a single entity Completed 22nd July 2010 22nd July 2010 0
B1G1 World Widget implementation framework Completed 22nd July 2010 22nd July 2010 0
Draft interface layout (Prototype for B1G1 World, Widget and Facebook App) Completed 22nd July 2010 20nd July 2010 -2
Database Deployment Completed 18th July 2010 18th July 2010 0
4 Project Management
Knowledge Sharing (Adobe Flex/Facebook) Completed 27th July 2010 27th July 2010 0
Prepare Proposal Presentation Slides Completed 30th July 2010 30th July 2010 0
Milestone: Project Acceptance Completed 5th August 2010 5th August 2010 0
Review Project Schedule Completed 9th August 2010 9th August 2010 0
Milestone: End of Elaboration 1 Phase Completed 10th August 2010 10th August 2010 0

Iteration 3 - Elaboration 2 Phase

Task Modules Involved Status Expected date of completion Actual date of completion Day Overdue
1 Business Modeling
Review Class Diagram Completed 11th Aug 2010 11th Aug 2010 0
2 Requirements
Review Project Requirements Completed 12th Aug 2010 12th Aug 2010 0
Update wiki page check Completed 12th Aug 2010 12th Aug 2010 0
3 Design
Review ER/LD Diagrams Completed 12th Aug 2010 12th Aug 2010 0
4 Implementation
B1G1 World
XML Structure Standardization for plotting markers on map Completed 13th Aug 2010 13th Aug 2010 0
XML Structure Standardization for details for a particular marker Completed 14th Aug 2010 14th Aug 2010 0
XML Structure Standardization for relationships for a particular marker Completed 15th Aug 2010 15th Aug 2010 0
Populating geocode data Completed 15th Aug 2010 16th Aug 2010 1
B1G1 World Layout Completed 19th Aug 2010 20th Aug 2010 1
Individual entities' icons Completed 19th Aug 2010 19th Aug 2010 0
B1G1 World Facebook application
Automated Wallpost Notifications Framework Completed 19th Aug 2010 19th Aug 2010 0
Facebook application layout Completed 19th Aug 2010 21th Aug 2010 2
5 Testing
Test B1G1 World database connectivity Completed 22nd Aug 2010 22nd Aug 2010 0
Test B1G1 World Facebook application wall post function Completed 22nd Aug 2010 22nd Aug 2010 0
6 Project Management
Knowledge Sharing (Adobe Flex/Facebook) Completed 24th Aug 2010 24th Aug 2010 0
Milestone: End of Elaboration 2 Phase Completed 25th Aug 2010 25th Aug 2010 0

Iteration 4 - Construction 1 Phase

Task Modules Involved Status Expected date of completion Actual date of completion Day Overdue
1 Business Modeling
Review Class Diagram Completed 27th Aug 2010 27th Aug 2010 0
2 Requirements
Review Project Requirements Completed 28th Aug 2010 28th Aug 2010 0
Update wiki page check Completed 1st Sept 2010 1st Sept 2010 0
3 Design
Review ER/LD Diagrams Completed 27th Aug 2010 27th Aug 2010 0
4 Implementation
B1G1 World
Filter: By Regions Completed 4th Sept 2010 5th Sept 2010 1
Filter: Projects that the member gives Completed 4th Sept 2010 7th Sept 2010 3
Filter: Projects that the worthy cause member has Completed 7th Sept 2010 11th Sept 2010 4
Filter: Members and Worthy Cause Member that the project has Completed 9th Sept 2010 10th Sept 2010 1
Filter: Leverage of an individual member Completed 9th Sept 2010 13th Sept 2010 4
Details Layout for individual entities Completed 6th Sept 2010 6th Sept 2010 0
Giving Information Layout for B1G1 World Completed 9th Sept 2010 10th Sept 2010 1
B1G1 World Facebook application
Facebook like function Completed 4th Sept 2010 6th Sept 2010 2
Facebook share function Completed 13th Sept 2010 16th Sept 2010 3
Facebook invite function Completed 13th Sept 2010 16th Sept 2010 3
Wall post function (for contribution by companies) Completed 9th Sept 2010 9th Sept 2010 0
Causes Listing Page Completed 15th Sept 2010 16th Sept 2010 1
Individual Cause Page Completed 20th Sept 2010 20th Sept 2010 0
Facebook Analytics - Retriving Number of Likes Cron Job Completed 11th Sept 2010 11th Sept 2010 0
Main Page and Feedback Page (UI) Completed 8th Sept 2010 9th Sept 2010 1
Causes Listing and Individual Cause Page Layout Completed 8th Sept 2010 9th Sept 2010 1
5 Testing
6 Project Management

Iteration 5 - Construction 2 Phase

Task Modules Involved Status Expected date of completion Actual date of completion Day Overdue
1 Business Modeling
Review Class Diagram Completed 6th Oct 2010 6th Oct 2010 0
2 Requirements
Review Project Requirements Completed 6th Oct 2010 7th Oct 2010 0
Update wiki page check Completed 6th Oct 2010 7th Oct 2010 0
3 Design
Review ER/LD Diagrams Completed 6th Oct 2010 7th Oct 2010 0
4 Implementation
B1G1 World
Filter: Keyword Search Completed 8 Oct 2010 18 Oct 2010 1
B1G1 World Generic Widget Completed 8 Oct 2010 1120 Oct 2010 3
B1G1 World Customized Widget Completed 8 Oct 2010 11 Oct 2010 3
Recommendation Module Completed 17 Oct 2010 17 Oct 2010 0
Administrative Module
Geocoding control panel Completed 11 Oct 2010 13 Oct 2010 2
Recommendation List Completed 21 Oct 2010 23 Oct 2010 2
Login/Logout Function Completed 08 Oct 2010 08 Oct 2010 0
B1G1 World Widget with AddThis Completed 08 Oct 2010 08 Oct 2010 0
B1G1 World Facebook application
Did You Know function Completed 8 Oct 2010 08 Oct 2010 0
5 Testing
6 Project Management