Meeting Number: 16
Date: 17th March 2009
Time: 5:00 pm to 7:00 pm
Venue: SIS GSR 2.5
Members Present: Navin, Guan Long, Yash, Ayush, Paresh
Agenda: Feedback from Flow Charting exercise. Work Allocation for week 12. Things to be done week 12.
Issues raised | Issue Raised by | Assigned to | Deadline |
- Re-engineering the process based on new changes --> As-Is model --> Modeling the changes --> Reminders for tasks |
All | Yash/Guan Long | 20th March 2009/ 23rd March 2009 |
- PDF Generation --> Selection of templates for letter generation |
All | Navin/Ayush | 23rd March 2009 |
- Things to be done in Week 12 --> Preparation for UAT # 2 scheduled for 27th March --> Display Matrix for faculty tracking --> Data locks --> Poster due on 30th March
|
All | All | Week 12 |
- Update to Design Documents --> Class Diagram, DB Schema, Sequence Diagrams, Use Cases - Update to Risk List --> New updates to Risks
|
All | Paresh | 23rd March 2009 |