Iteration Change Initiator Description Management Strategy Verdict
5 Sponsor * Request to add “Peer Evaluation” module after acceptance
*Add to students and lecturer functions
*Checked in with developers to see if they can manage the new function
*Check with PM if schedule can accommodate the new function
Accepted
7 Team * Lost 2 key developers in the team * Reshuffled roles
  • Allocated a backup roles
  • Negotiated for scope reduction
Accepted
9 Sponsor * Top priority for now till finals is to improve UI to promote usability *Checked in with developers to see if they can manage the new function
  • Check with PM if schedule can accommodate the new function
Accepted
9 Faculty * To include 2 mobile features based on acceptance feedback *Checked in with developers to see if they can manage the new function
  • Check with PM if schedule can accommodate the new function
Accepted
9 Team * To incorporate "Offline Function" *Checked in with developers to see if they can manage the new function
  • Check with PM if schedule can accommodate the new function
  • Check with sponsor if ok
  • Dropped "Survey Module"
Accepted