Task Metrics

We used a combination of task metric calculations and a burndown chart to track our progress of task completion through the project.

In terms of task metrics, we used 2 main measures to track our task completion through the project

1. Quantitative Task Metric Measure to gauge task estimation efforts and appropriate action taken to address any over/underestimations

2. Overall Project Burndown Chart to visually represent the actual completion rate of tasks in comparison to the overall number of project tasks


Calculation of Task Metric Score

Task Metric Score = (Actual Tasks Completed / Planned Tasks to Complete) x 100%


Score Action
< 50% Team is very significantly behind schedule, advise contacting supervisor for advice, re-estimation of tasking and dropping of non-essential functionality.
50% to 90% Team is behind schedule, consider number of tasks attempted and circumstances, advise re-estimation of tasking.
90% to 110% Team is on schedule, carry on with current estimation of tasks.
110% to 150% Team is behind schedule, consider number of tasks attempted and circumstances, advise re-estimation of tasking.
> 150% Team is very significantly behind schedule, advise contacting supervisor for advice and re-estimation of tasking and dropping of non-essential functionality.


Iteration Number Of Tasks Total Complete Completed within the same iteration Completed within a different iteration Planned Cumulative Task Count Actual Cumulative Task Count Task Metrics Action
0 - - - - 98 98 - -
1 2 2 2 0 96 96 100% Team is on schedule, carry on with current estimation of tasks.
2 6 4 4 2 90 92 67% Team is behind schedule, consider number of tasks attempted and circumstances, advise re-estimation of tasking.
3 5 5 4 1 85 87 80% Team is behind schedule, consider number of tasks attempted and circumstances, advise re-estimation of tasking.
4 3 4 2 1 82 83 67% Team is behind schedule, consider number of tasks attempted and circumstances, advise re-estimation of tasking.
5 9 8 7 0 73 75 78% Team is behind schedule, consider number of tasks attempted and circumstances, advise re-estimation of tasking.
6 47 32 32 1 26 43 68% Team is behind schedule, consider number of tasks attempted and circumstances, advise re-estimation of tasking.


CodeBenders Task.png


Bug Metrics

Calculation of Impact Score

Total = 1 x num (low) + 5 x num (high) + 10 x num (critical)

Severity Description
Low Impact (Score: 1) Inconsequential. Simple typo error or minor user interface misalignment.
High Impact (Score: 5) Non-critical functionalities are not working, but still system runs.
Critical Impact (Score: 10) The system or core functionality is down. Immediate attention is required

Mitigation Plan

Points in Iteration Action
Points =< 10 Fix during buffer time only.
10 < Points < 20 Use the planned debugging time.
Points >= 20 Stop current development and resolve the bug immediately. Reschedules the project.


Iteration Impact
Low High Critical
1 0 0 0
2 0 0 0
3 0 0 0
4 0 0 0
5 0 0 0
6 7 0 0
7 - - -
8 - - -
9 - - -
10 - - -
11 - - -
12 - - -
13 - - -
14 - - -
15 - - -