Iteration | Planned Duration (Hours) | Actual Duration (Hours) | Task Metrics Score (%) | Action | Status |
---|---|---|---|---|---|
1 | 271.2 | 279.6167 | 96.9899 | Estimates are generally accurate and on track. | Completed |
2 | 164 | 161 | 101.8634 | Estimates are generally accurate and on track. | Completed |
3 | 85 | 87 | 97.7011 | Estimates are generally accurate and on track. | Completed |
4 | 115.2 | 113 | 101.9469 | Estimates are generally accurate and on track. | Completed |
5 | 163 | 150.5 | 108.2353 | Estimates are generally accurate and on track. | Completed |
6 | 147.5 | 148.5 | 95.9596 | Estimates are generally accurate and on track. | Completed |
7 | 159.5 | 155.5 | 102.5723 | Estimates are generally accurate and on track. | Completed |
8 | 158 | 150.5 | 104.9834 | Estimates are generally accurate and on track. | Completed |
9 | 149.5 | 144.5 | 103.4602 | Estimates are generally accurate and on track. | Completed |
10 | 147 | 147 | 100 | Estimates are generally accurate and on track. | Completed |
11 | 144 | 144 | 100 | Estimates are generally accurate and on track. | Completed |
12 | 144 | 144 | 100 | Estimates are generally accurate and on track. | Completed |