Codex Final Task Metrics.png


Iteration Period Task Metric Score Actions
1
4 October 2015 - 13 Oct 2015
100%
As planned.
2
13 Oct 2015 - 26 Oct 2015
100%
As planned.
3
26 Oct 2015 - 12 Nov 2015
92.30%
A part of Order Management - Payment Process - Paypal function was delayed and moved to Iteration 7 because our coder used the time to do bugs squashing for User Management until it was at an acceptable bug score instead.
4
12 Nov 2015 - 4 Dec 2015
100%
As planned.
5
4 Dec 2015 - 20 Jan 2016
93.75%
Human risk happened. Team member has to go back to china earlier than planned, hence, we decided to move the Inventory Management - Low Stock Warning to Iteration 7
6
20 Jan 2016 - 10 Feb 2016
100%
As planned.
7
10 Feb 2016 - 28 Feb 2016
100%
As planned.
8
29 Feb 2016 - 9 Mar 2016
87.50%
UAT2 was delayed and pushed to Iteration 9, as Client delayed giving us the real product photos for the actual UAT2.
9
10 Mar 2016 - 24 Mar 2016
100%
As planned.
10
25 Mar 2016 - 8 April 2016
100%
As planned.
11
8 April 2016 - 14 April 2016
100%
As planned.


Codex Final Bug Metrics.png


Iteration Bug Score Summary of Bugs Action Taken
1
0
There is no planned and actual testing done. We decided to focus on Acceptance development.
No action taken.
2
0
There is no planned and actual testing done. We decided to focus on Acceptance development.
No action taken.
3
37
The first testing is done and is for a major part of our development, the User Management Module, hence the surge in bugs. We discovered 4 high impact bugs and 17 low impact bugs. Low impact bugs were from the UI Error Messages.
Coders stopped all current development and resolve the bugs.
4
10
2 high impact bugs due to unable to process adding and editing of product should an unacceptable input be keyed in.
Coders stopped all current development and resolve the bugs.
5
6
1 high impact bugs and 1 low impact bug found in Order and Inventory Management Module, mainly from View Order History Page.
Developers to use planned debugging time in the iteration to solve the bug.
6
0
There is no planned and actual testing done in this iteration.
No action taken.
7
13
2 High Impact Bugs from session and redirecting problems. 3 low impact errors discovered during our UAT.
Coders stopped all current development and resolve the bugs.
8
17
2 Low impact bugs and 3 High Impact Bugs found. Low impact bugs arises from UI, high impact Bugs comprises of our input validation issues.
Coders stopped all current development and resolve the bugs.
9
0
There is no planned and actual testing done in this iteration.
No action taken.
10
22
2 High Impact Bugs and 12 Low Impact Bugs found from testing of new Functions as well as regression testing.
Coders stopped all current development and resolve the bugs.
11
0
End of project.