Project Progress Summary

Mid Terms Slides: here

website url: www.lasercommerce.com

Summary of Project:

Total Iterations: 11
Completed Iterations: 7
Based on our estimates, 75% of the project is done.
Website is deployed live and we are currently developing mobile.
We are confident to complete project on schedule.

Project Highlights:

Unexpected Events:

Unexpected Events Action taken
Iteration 4 was delayed Followed our mitigation plan and readjusted schedule
Kevin's laptop was spoiled for 2 weeks in iteration 3 Borrowed another laptop to use

Project Management

Project Status:

Changes

Inception Mid Term Progress.png

Project Schedule:


Changes in project architecture since acceptance, changing the way some functions are completed.
Everything is on schedule.
Delay in iteration 4 and Iteration 5 (buffer iteration) was ahead, so schedule is balanced back.
Currently in Iteration 9, doing UI Adjustments for mobile.

Inception Schedule.PNG

Project Metrics:

Metrics

Bug Metrics: We have 2 iterations, iteration 1 and 2 of bug score above 40. While the other iterations are okay.
Schedule Metrics: Iteration 4 have a SM score of 0.7 as google analytics implementation was more difficult than expected and iteration 5 has a SM score of 1.3 as it was a buffer iteration and all the changes from acceptance and UT 2 were done on time. All the other iterations have a SM score of 1.0.

Project Risks:

Inception Risk Mid Terms.png

Technical Complexity:

Architecture

Inception Architecture Diagram.PNG

1. Cordova Framework (iOS + Android Plugins)

InceptionComplexity1.PNG
InceptionComplexity2.PNG
InceptionComplexity3.PNG
InceptionComplexity4.PNG

2. Google Analytics + Google Visualization
InceptionComplexity5.PNG
InceptionComplexity6.PNG
InceptionComplexity7.PNG
InceptionComplexity8.PNG
InceptionComplexity9.PNG
InceptionComplexity10.PNG
InceptionComplexity12.PNG
InceptionComplexity13.PNG
File:InceptionComplexity14.PNG
File:InceptionComplexity15.PNG
3. Paypal Implementation
InceptionComplexity11.PNG

Quality of Product

Intermediate Deliverables:

Stage Specification Modules
Project Management Minutes Minutes
Metrics Schedule & Bug Metrics
Risk Metrics Risk Metrics
Change Management Change Management
Requirements Market Research Market Research
Analysis & Design Navigation, Use Case and Architecture Diagram Diagrams
Testing User test plan User Test 1

User Test 2 User Test 3

Deployment:

Our website deployed linked: http://www.lasercommerce.com

Testing:

Functional Testing Done after every Iteration User Testing done

User Testing Date Venue No. Of Users Link
1 12th - 15th July At Tester's Convenience 30 B2C Users, 5 B2B Users User Testing 1 Link
2 8th August Client's Office 3 User Testing 2 Link
3 12th September SIS GSR 2-7 6 User Testing 3 Link

Reflection

Team Reflection

Inception Mid Term Learning Outcome.png