SCHEDULE METRICS TASK METRICS BUG METRICS


What: Task metrics are used to measure the team's progress when completing tasks.
When: It is measured at the end of each task.
How: Planned number of hours/Actual number of hours

Score Action
TM <= 0.9 Team is behind the schedule. Effort required to complete task is under-estimated.
  1. Re-estimate tasks for future iterations
  2. Deduct the number of days behind schedule from buffer days
  3. If there is no more buffer day, decide the functionalities to drop
0.9 < TM <= 1.1 Estimates are fairly accurate and team is on schedule.
TM > 1.1 Team is ahead of schedule. Effort required to complete task is over-estimated.
  1. Re-estimate tasks for future iterations
  2. Add the number of days gained to buffer days


Task Metrics Results


6nificanceTaskMetric.PNG


Task Hours


6nificanceTaskMetric(Hours).PNG

Summary of Task Metrics

Iteration 1
Iteration 2
Iteration 3
Iteration 4
Iteration 5
Iteration 6
Iteration 7
Iteration 8
Iteration 9
Iteration 10
Iteration 11