IS480 Team wiki: 2015T6 6nificance Metrics
Project Schedule | Metrics | Risks | Change Management |
SCHEDULE METRICS | TASK METRICS | BUG METRICS |
---|
What: Schedule metrics are used to measure the progress of project.
When: It is measured at the end of each iteration.
How: Planned number of days/Actual number of days
Score | Action |
---|---|
SM <= 0.9 | Team is behind the schedule. Effort required to complete is under-estimated.
|
0.9 < SM <= 1.1 | Estimates are fairly accurate and team is on schedule. |
SM > 1.1 | Team is ahead of schedule. Effort required to complete is over-estimated.
|
Schedule Metrics Results
Summary of Schedule Metrics
Iteration | Planned Duration (Days) | Actual Duration (Days) | Schedule Metric Score | Action Taken | Status |
---|---|---|---|---|---|
1 | 14 | 23 | 0.61 | More time needed to apply new concepts of android development, Google Cloud Services and Facebook login. More time also needed to debug identified bugs of high impact during testing. Follow up action: Informed supervisor about delay. Re-scheduled the dates and tasks of iterations 2, 3 and 4. More coders have also been temporarily deployed and a temporary job roles swap has been made until Acceptance Presentation. |
Completed |
2 | 12 | 14 | 0.86 | More time needed to complete the detect photo color function of Design Module as well as optimizing UI development for Design Module to include RGB sliders. Follow up action: Informed supervisor about delay. Re-scheduled the dates and tasks of iterations 3 and 4. Reduced duration of iteration 3 and 4 from 10 days to 9 days. |
Completed |
3 | 9 | 9 | 1.00 | Estimates are generally accurate and on track. Proceed as per normal. | Completed |
4 | 9 | 9 | 1.00 | Estimates are generally accurate and on track. Proceed as per normal. | Completed |
5 | 14 | 16 | 0.88 | More time needed to complete Update Profile function due to difficulties with uploading images to cloud database. Follow up action: Informed supervisor about delay. Re-scheduled the dates and tasks of iteration 6. Reduced duration of iteration 6 from 14 days to 12 days. More coding hours per day were allocated in iteration 6. |
Completed |
6 | 12 | 14 | 0.86 | More time needed to research and complete Social Module due to complexity with creating a new social media platform from scratch. Follow up action: Informed supervisor about delay. Re-scheduled the dates and tasks of iteration 7. Removed 2 buffer days in iteration 8. |
Completed |
7 | 14 | 16 | 0.88 | More time needed to debug bugs found in newsfeed and view color hashtag of social module Follow up action: Informed supervisor about delay. Reduced duration of iteration 8 from 9 days to 7 days. |
Completed |
8 | 7 | 7 | 1.00 | Estimates are generally accurate and on track. Proceed as per normal. | Completed |
9 | 17 | 19 | 0.89 | More time needed to optimize loading speed of images and sorting color algorithm Follow up action: Informed supervisor about delay. Reduced duration of iteration 10 from 14 days to 12 days. |
Completed |
10 | 12 | 13 | 0.92 | Estimates are generally accurate and on track. Proceed as per normal. |
Completed |
11 | 14 | 14 | 1.00 | Estimates are generally accurate and on track. Proceed as per normal. |
Completed |