Overall Schedule Metrics Chart

Overall sm score.png
Iteration Planned Days Actual Days SM Score Action

1

42

41

102.43

Proceed as normal

2

14

14

100

Proceed as normal

3

14

13

107.69

Proceed as normal

4

21

21

100

Proceed as normal

5

14

21

66.67

  • Continue task into iteration 6
  • Revise scope and schedule for Iteration 6 & 7
  • Delay caused due to change in user requirement
  • Chin Chye's laptop was down for repair

6

14

20

70

  • Continue task into iteration 7
  • Revise schedule for all further Iterations
  • Delay caused due to underestimation of time required for revamping the functions from scratch

7

14

15

93.33

Proceed as normal

8

14

14

100

Proceed as normal

9

14

15

93.33

Proceed as normal

10

14

14

100

Proceed as normal

11

14

15

93.33

Proceed as normal

12

14

13

107.69

Proceed as normal

13

14

14

100

Proceed as normal

14

14