IS480 Team wiki: 2015T1 Vulcan Project Management
Jump to navigation
Jump to search
We are currently at Iteration 10.
HOME | ABOUT US | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION |
Simplified Project Schedule
Iteration | Date | Milestones | Status |
---|---|---|---|
0 | 18 May 2015 - 17 Jun 2015 | Proposal (17 Jun 2015) | Completed |
1 | 18 Jun 2015 - 5 Jul 2015 | Completed | |
2 | 7 Jul 2015 - 7 Aug 2015 | Completed | |
3 | 8 Aug 2015 - 17 Aug 2015 | User Testing 1 (13 Aug 2015) Acceptance (17 Aug 2015) |
Completed |
4 | 18 Aug 2015 - 10 Sep 2015 | Registration (20 Aug 2015) | Completed |
5 | 11 Sep 2015 - 24 Sep 2015 | User Testing 2 (18 Aug 2015)
User Testing 3 (22 Aug 2015) |
Completed |
6 | 25 Sep 2015 - 8 Oct 2015 | Mid Term (7 Oct 2015)
Alpha Launch on Playstore / Testing (2 Oct 2015) |
Completed |
7 | 9 Oct 2015 - 22 Oct 2015 | Completed | |
8 | 23 Oct 2015 - 5 Nov 2015 | User Testing 4 (23 Oct 2015) | Completed |
9 | 6 Nov 2015 - 19 Nov 2015 | User Testing 5 (6 Nov 2015) UAT (6 Nov 2015) |
Completed |
10 | 20 Nov 2015 - 3 Dec 2015 | Finals (23 Nov 2015) Poster Day (3 Dec 2015) |
In Progress |
Project Schedule