Our team spent a significant amount of time improving the UI of 8 application forms (which have different amount of questions and validations)
Our team's AWS server encountered unknown software exploit issues - resulting in the delay of our web application deployment
Conducted 2 User Tests and soft launch of our web application.
Change request to include hover-over information function to most questions in 8 application forms
Completion of Primary Function Modules: 85%
Completion of Secondary Function Modules: 70%








Main Wiki | Midterm Wiki | Final Wiki |
---|
Contents
Project Progress Summary
Mid Terms Slides:
Click here for Mid-Term Presentation Slides.
Project Highlights:
Project Management
Project Status:

Planned Schedule:
![]() |
![]() |
Actual Schedule:
![]() |
![]() |
Project Metrics

Highlights of Schedule Metrics
Iteration | Planned (Days) | Actual (Days) | SM Score | Action | Status |
---|---|---|---|---|---|
22 | 28 | 78% | Team is behind schedule due to team members being overseas and complexity of generating certificate based on given template. As a result team was unable to test and integrate in time. Mitigation was done by deducting the number of days behind schedule from buffer days. | Completed |

Highlights of Bug Metrics
Iteration | Bug Score | Number of Issues | Summary of Bugs and Issues | Action Taken |
---|---|---|---|---|
1 High Impact Bugs & 3 Critical Impact Bugs | Bugs present are related to the viewing and validations of the application forms. | Critical impact to application's usability. Resolve bugs immediately. |
Project Risks:

Technical Complexity:




Quality of Product
Intermediate Deliverables:
Type | Specification | Documentation |
---|---|---|
Project Management | Minutes | Minutes |
Metrics | Schedule Metrics | |
Analysis | Use case | Use Case Diagram |
Business Process Diagram | Business Process Diagram | |
Design | Architecture Diagram | Architecture Diagram |
Database Diagram | Database Diagram | |
Testing | User Test Plan | User Test 1 Document |
Testing:
User Testing 1:
Objectives:
- Discover usability issues of the web application
- Obtain feedback by testers regarding functionalities and user interface
- To improve web application based on UT1 results
Number of Users: 3 (Sponsor, and 2 industry testers from Green Transformation Lab)
Venue: SMU SIS GSR 2-1
Date: 28 October 2015
Duration: 40 mins per user
Scope of UT1:
- Registration
- Login/Logout
- Application form for 1-Leaf to 4-Leaf GFA Label (Shipper and Carrier)
Find out more about our User Testing 1 Results here
User Testing 2:
Objectives:
- Average Success Rate of main tasks to be > 85%
- Gather feedback on User Experience
- Critique UI Layout
Number of Users: 4 (Sponsor, and 3 Industry Testers)
Venue: SMU SIS GTL Lab
Date: 18 February 2016
Duration: 40 mins per user
Scope of UT2:
- Registration
- Login/Logout
- Data Collection and Validation Module
- Assessment Module
- Certificate Generation Module
- Notification and Tracking Module
User Testing 2 Results
Feedback | |
---|---|
|
Learning Outcomes
![]() |
![]() |
![]() |
![]() |
![]() |