Project Schedule
- Updated on 19 November 2014
Changes
- Add "Reuse existing documents in multiple programs (participant)" to Iteration 9
- Add "End User Training" on 27 Nov
Check our archived schedule
Change Log
S/N | Change Event | Category | Requester | Priority | Impact Level |
---|---|---|---|---|---|
1 | Change the name from "Notification Email" to "Automatic Email Notification" | Modify functionality name | Team | Low | No Impact |
2 | Add "View list of Application" to Iteration 3 | Add functionality | Sponsor | Medium | Medium |
3 | Move "Accept Application" from Iteration 3 to Iteration 4 | Move functionality | Team | Low | Low |
4 | Move "Withdraw from Program" from Iteration 3 to Iteration 5 | Move functionality | Team | Low | Low |
5 | Move "CRUD email templates" from iteraion 4 to iteration 5 | Move functionality | Team | Low | Low |
6 | Add "Search Program" to Iteration 5 | Add functionality | Sponsor | Medium | Low |
7 | Remove "Create, View Program Page Template" from Iteration 5 | Remove functionality | Sponsor | Low | No Impact |
8 | Remove "Update Program Page Template" from Iteration 6 | Remove functionality | Sponsor | Low | No Impact |
9 | Move "Track Application Progress" from Iteration 5 to Iteration 6 | Move functionality | Sponsor | Medium | Medium |
10 | Add "Custom Email for Stakeholders" to Iteration 6 | Add functionality | Sponsor | Low | High |
11 | Move "Track Application Progress" from Iteration 5 to Iteration 6 | Add functionality | Sponsor | Medium | Medium |
12 | Add "Archive Program" to Iteration 2 | Add functionality | Team | Medium | Low |
13 | Move "Update, Delete Program" from Iteration 3 to Iteration 2 | Move functionality | Team | Low | Low |
14 | Move "Search Program" from Iteration 3 to Iteration 2 | Move functionality | Team | Low | Low |
15 | Add "Appy to Program" to Iteration 2 | Add functionality | Sponsor | High | High |
16 | Move "View list of application" from Iteration 3 to Iteration 2 | Move functionality | Team | Low | Low |
17 | Remove "Delete Registration Form" from Iteration 4 | Move functionality | Sponsor | Low | No Impact |
18 | Move "Accept Application", "Reject Application" from Iteration 4 to Iteration 3 | Move functionality | Team | Medium | High |
19 | Move "Withdraw from Program" from Iteration 5 to Iteration 3 | Move functionality | Team | Medium | High |
20 | Move "Track Application Progress" from Iteration 6 to Iteration 3 | Move functionality | Sponsor | Medium | High |
21 | Move "Delete Documents" from Iteration 4 to Iteration 3 | Move functionality | Team | Low | Low |
22 | Add "Download Documents" to Iteration 3 | Add functionality | Sponsor | High | Medium |
23 | Add "Send Automatic Emaill at Application Status Change" to Iteration 4 | Move functionality | Sponsor | High | High |
24 | Move "Auto-Schedule Email" from Iteration 7 to Iteration 4 | Move functionality | Sponsor | Low | High |
25 | Add "Role-based Authorization for Teachers" from Iteration 7 to Iteration 4 | Add functionality | Sponsor | High | High |
26 | Move "Login/Logout (Facebook)" from Iteration 4 to Iteration 5 | Move functionality | Team | Low | Low |
27 | Move "Administratior Dashboard" from Iteration 7 to Iteration 5 | Move functionality | Sponsor | Low | Low |
28 | Move "Upload Document" from Iteration 4 to Iteration 2 | Move functionality | Team | Medium | Low |
29 | Move "Read Document" from Iteration 4 to Iteration 5 | Move functionality | Sponsor | Medium | Medium |
30 | Move "Export selective participant data" from Iteration 7 to Iteration 5 | Move functionality | Sponsor | High | High |
31 | Add "View List of documents by Program" to Iteration 5 | Add functionality | Sponsor | Low | Low |
32 | Move "CRUD email Templates" from Iteration 7 to Iteration 6 | Move functionality | Team | Low | Low |
33 | Add "Analyze Participant Data", "Analyze Program Data" to Iteration 7 | Add functionality | Team | Low | Medium |
34 | Move "Release of version 0.3" from Iteration 8 to Iteration 6 | Move functionality | Team | Medium | Low |
35 | Shift "User Testing #1" from 30 Jul to 05 Aug | Shift milestone | Sponsor | Medium | Low |
36 | Shift "User Testing #2" from 27 Sep to 22 Sep | Shift milestone | Sponsor | Medium | Low |
37 | Add "User Testing #3" on 14 Oct | Add milestone | Team | Medium | Medium |
38 | Shift "User Testing #4" from 17 Nov to 10 Nov | Shift milestone | Team | Low | Low |
39 | Add "Go Live #1" on 29 Sep | Add milestone | Supervisor | High | Medium |
40 | Add "Go Live #2" on 16 Nov | Add milestone | Supervisor | High | Medium |
41 | Shift "Mid-term Presentation" from 3 Oct to 9 Oct | Shift milestone | NA | High | Low |
42 | Shift "Final Presentation" from 28 Nov to 29 Nov | Shift milestone | NA | High | Low |
43 | Shift "Poster Submission" from 12 Nov to 10 Nov | Shift milestone | NA | High | Low |
44 | Shift "Poster Day" from 06 Dec to 03 Dec | Shift milestone | NA | High | Low |
45 | Shift Midterm Date from 09 Nov to 10 Nov | Shift milestone | NA | High | Low |
46 | Shift " User Testing #4" from 14 Nov to 16 Nov | Shift milestone | Team | Medium | Low |
47 | Shift "Go Live #2" from 23 Nov to 25 Nov | Shift milestone | Team | Medium | Medium |
48 | Extend Iteration 9: 12 Nov - 25 Nov (previously: 12 Nov - 30 Nov) | Extend iteration | Team | Medium | High |
49 | Add "System Testing and Debugging", "System Improvement" to Iteration 9 | Add functionality | Team | Medium | High |
50 | Move "Email Module" from Iteration 6 to Iteration 7 | Move functionality | Sponsor | Low | Low |
51 | Move "Account Module" from Iteration 7 to Iteration 6 | Move functionality | Sponsor | Low | Low |
52 | Shift "User Testing #4" from 17 Nov to 10 Nov | Add functionality | Sponsor | High | High |
53 | Remove "Role-based authorization for parents" from Iteration 5 | Remove functionality | Sponsor | Low | Low |
54 | Add "Reuse existing documents in multiple programs (admin)" to Iteration 6 | Add functionality | Sponsor | Medium | High |
54 | Move "Export selective participant data" from Iteration 5 to Iteration 6 | Move functionality | Team | Medium | Medium |
54 | "Add "Upload documents from multiple locations" to Iteration 7 | Add functionality | Sponsor | Medium | High |
54 | "Add "Add multiple agreements in registration form" to Iteration 8 | Add functionality | Sponsor | High | High |
54 | Add "Duplicate registration form" to Iteration 8 | Add functionality | Sponsor | High | Medium |
54 | Add "Update Profile info from application form" to Iteration 8 | Add functionality | Reviewer | Low | Low |
54 | Add "Reuse existing documents in multiple programs (participant)" to Iteration 9 | Add functionality | Sponsor | Medium | Medium
|
54 | Add "End User Training" on 27 Nov | Add milestone | Team | Medium | High |