Project Timeline & Milestones

Latest version

Timeline OnePieceFinal.jpg

Previous version

V3

Version 3


Description

  • Add Quiz function mark allocation feature (Reason: new user requirement)
  • Shaded completed modules
  • Fixed according to acceptance feedback


V2

Version 2


Description

  • No modification on project planning
  • Re structured the timeline layout
  • Added accurate milestones with detailed module description


V1

Version 1


Description

  • Gathered basic user requirements and developed prototypes as IDP project last term (2014 Term 2)
  • Resume project on early June (Summer) and end by mid December
  • Every 15 days is one iteration and total of 15 iterations
  • Total of 6 milestones including three UATs