Risk & Mitigation Plan (2013)
Description | Impact on Project | Probability | Severity | Risk Reduction/Mitigation Strategy |
Higher effort to balance same workload with less resources | Time & Quality | Medium | High | PM (together with team) will readjust schedules to fit extra time with training; team to do peer learning process |
High Expectation of change or additional requests from client | Time & Quality | High | Medium | Change request log is created to manage change requests more effectively |
Steep Learning Curve for Titanium | Quality | High | High | PM will assign 1 day for everyone to coach the team. If necessary, stop current development in other aspects. |
Risk & Mitigation Plan (2012)
Description | Impact on Project | Probability | Severity | Risk Reduction/Mitigation Strategy |
Incompatibility with iOS 6 | Quality | Medium | Medium | Team to research current version of Xcode on iOS 6 compatibility |
Lack of knowledge in iOS development | Time and Quality | High | Medium | Team members to seek help or self-learn immediately. Team is currently outsourcing in iOS Tutorial Video |
Team's current commitment to current school term might disrupt development of project | Resource | High | Medium | Team to adhere project schedule strictly. PM meets team (as a group or individually) to track progress |