After Mid Term Schedule

Functions Key Personnel Plan Schedule Actual Schedule Remarks
Iteration 6 15 Oct - 2 Nov 15 Oct - 3 Nov
Documentation
  • Update Use Case
Zou Mei 15 Oct 15 Oct Completed
  • Update Domain Diagram
Shoe 15 Oct 15 Oct Completed
  • Create Test Cases for Credit Management
Jasmine 15 Oct 15 Oct Completed
Development
Credit Management Ryan 80% Completed
  • View Credit Balance
16 Oct - 29 Oct 30 Oct Completing in Iteration 7
  • Add Credit
16 Oct - 29 Oct 30 Oct Completing in Iteration 7
  • Remove Credit
16 Oct - 29 Oct 30 Oct
  • Extract Credit
16 Oct - 29 Oct 30 Oct
User Management Zhen Guang Functionality Dropped
  • Ratings
16 Oct - 29 Oct Not Completed
Spree Management Completed
  • Notification Center (Payment Verification)
Zhen Guang 16 Oct - 29 Oct 30 Oct
  • Back-End Logic Component
Ryan 16 Oct - 29 Oct 30 Oct
Unit Testing
  • Testing
Zou Mei 30 Oct 31 Oct Completed
  • Document Test Cases
Qian Hwee 30 Oct 31 Oct Completed
Integration
  • Integration
Ryan 31 Oct - 1 Nov 2 Nov Completed
  • Debugging
Zhen Guang 31 Oct - 1 Nov 2 Nov Completed
Deployment
  • Testing
Shoe 2 Nov 3 Nov Completed
  • Document Full Test Cases
Jasmine 2 Nov 3 Nov Completed
Buffer 2 Nov - 4 Nov 1 Buffer day used
Iteration 7 5 Nov - 16 Nov 5 Nov - 17 Nov
Documentation
  • Update Use Case
Qian Hwee 5 Nov 5 Nov Completed
  • Update Domain Diagram
Jasmine 5 Nov 5 Nov Completed
  • Create Test Cases for Social Integration
Zou Mei 5 Nov 5 Nov Completed
Development
Social Integration Zhen Guang, Qian Hwee 90% Completed
  • Login Through Facebook
6 Nov - 12 Nov 8 Nov
  • Sharing of Favorites through Facebook
6 Nov - 12 Nov 12 Nov
  • Embedding Widgets
6 Nov - 12 Nov Not Completed Shift to Iteration 8
Credit Management Ryan Completed
  • View Credit Balance (For Participants)
6 Nov - 12 Nov 13 Nov
  • Add Credit (For Participants)
6 Nov - 12 Nov 13 Nov
Unit Testing
  • Testing
Shoe 13 Nov 14 Nov Completed
  • Document Test Cases
Zou Mei 13 Nov 14 Nov Completed
Integration
  • Integration
Zhen Guang 14 Nov - 15 Nov 16 Nov Completed
  • Debugging
Ryan 14 Nov - 15 Nov 16 Nov Completed
Deployment
  • Testing
Jasmine 16 Nov 17 Nov Completed
  • Document Full Test Cases
Shoe 16 Nov 17 Nov Completed
Buffer 17 Nov 1 Buffer day used
Iteration 8 18 Nov - 29 Nov 18 Nov - In Progress
Documentation
  • Update Use Case
Shoe 18 Nov 18 Nov Completed
  • Update Domain Diagram
Zou Mei 18 Nov 18 Nov Completed
  • Create Test Cases for Backend Admin Functions
Jasmine 18 Nov 18 Nov Completed
Development
Backend Admin Functions
  • Audit Trial (Log)
Ryan 19 Nov - 25 Nov 25 Nov Completed
Tag and Bag Framework (Plugin)
  • Error Reporting
Zhen Guang 19 Nov - 25 Nov 25 Nov Completed
Social Integration
  • Embedding Widgets
Qian Hwee 19 Nov - 25 Nov 25 Nov Completed
Backend
  • Ability Functions
Ryan 19 Nov - 25 Nov 25 Nov Completed
Unit Testing
  • Testing
Jasmine 26 Nov 26 Nov Completed
  • Document Test Cases
Shoe 26 Nov 26 Nov Completed
Integration
  • Integration
Zhen Guang 27 Nov - 28 Nov 28 Nov Completed
  • Debugging
Ryan 27 Nov - 28 Nov 28 Nov Completed
Deployment
  • Testing
Qian Hwee 29 Nov 29 Nov Completed
  • Document Full Test Cases
Zou Mei 29 Nov 29 Nov Completed
Buffer 30 Nov - 5 Dec