Schedule

Progress

Project Schedule

Schedule (NEW) OHW.png Our Progress.png

Iteration Planned (Before Acceptance Presentation) Actual (Actions taken during current iteration) Remarks
4

Start Date: 20/08/2012
End Date: 02/09/2012

  • Amendments from Acceptance's feedback
  • Heuristic Evaluation preparation
  • Implementation: Apply job (Email function) & Login (OAuth) modules

Start Date: 20/08/2012
End Date: 02/09/2012

  • Amendments from Acceptance's feedback
  • Heuristic Evaluation preparation
  • Implementation: Manage job application + Call for interview function

Task(s) delayed:

  • Implementation: Apply job (Email function)
  • Implementation: Login (OAuth)

Reasons:

  • More time was taken up in the amendments of Acceptance’s feedback task
  • Team had decided to move up Iteration 5's functions: Manage job application + Call for interview modules to the current iteration.
  • Team had decided to allocation some time in exploring OAuthentication (Create login page & data extraction – LinkedIn)function which will be implemented in the next Iteration.
5

Start Date: 03/09/2012
End Date: 16/09/2012

  • Amendments from Heuristic Evaluation's feedback
  • UT 1 preparation
  • Implementation: Manage job history & manage job post (tagging) modules

Start Date: 03/09/2012
End Date: 23/09/2012

  • Amendments from Heuristic Evaluation's feedback
  • UT 1 preparation
  • Implementation: - Login (OAuthentication) & Data Extraction -Administrator - Login + Deactivate account

Task(s) delayed:

  • Implementation: Manage job post (Tagging)
  • Implementation: Login (OAuthentication)

Reasons:

  • Team had decided to move up Iteration 6's function: Administrator - Login + Deactivate account to the current iteration.
  • Team had allocated more time in conducting internal testing and debugging session before pushing the application out for User Testing 1.
  • Team had decided to allocation some time in exploring the functions for Collaborative Reviews

6

Start Date: 17/09/2012
End Date: 30/09/2012

  • Amendments from UT1's feedback
  • Mid-Term preparation
  • Implementation:Deactivate account & manage job application (filter) modules

Start Date: 24/09/2012
End Date: 07/10/2012

  • Amendments from UT1's feedback
  • Mid-Term preparation
  • Implementation: Apply Job (Send Email to external party), Design minutes.io style (resume template), Sort function

Task(s) delayed:

  • Implementation: Manage job post (Tagging)

Reasons:

  • Team had decided to implemented the delayed task from Iteration 4: Apply job (Send email to external party function)
  • Team had decided to implemented a minor 'Sort' function to improve user's experience.
  • Team had started designing a sample template of minutes.io style (resume template) as part of client's requirements.


Detailed Schedule Breakdown:

Planned Actual
Iteration Task Start End Task Start End Remark
0 Research on various framework (Spring, Play! Etc) 14/5/2012 20/5/2012 Research on various framework (Spring, Play! Etc) 14/5/2012 27/5/2012
1 CRUD login page - Social Media Authentication 23/6/2012 27/6/2012 CRUD login page - Social Media Authentication 23/6/2012 - Incomplete; unable to perform data extraction.
Task was postponed to Iteration 4 (After Acceptance).
CRUD resume (standard template) page 25/6/2012 4/7/2012 CRUD resume (standard template) page 25/6/2012 9/7/2012
2 Integration & Deployment of codes to client's server 28/7/2012 29/7/2012 Integration & Deployment of codes to client's server 30/7/2012 2/8/2012
3 Implementation - Multiple fields to resume template 5/8/2012 10/8/2012 Implementation - Multiple fields to resume template 5/8/2012 13/8/2012
4 Amend changes from Acceptance's feedback 20/8/2012 29/8/2012 Amend changes from Acceptance's feedback 20/8/2012 2/9/2012
CRUD job application + 'call for interview' function 27/8/2012 29/8/2012 CRUD job application + 'call for interview' function 27/8/2012 2/9/2012
5 Amend changes from Heuristic Evaluation (Functionalities + User Interface) 3/9/2012 17/9/2012 Amend changes from Acceptance's feedback (Functionalities + User Interface) 3/9/2012 17/9/2012
Internal Testing 14/9/2012 16/9/2012 Internal Testing 14/9/2012 18/9/2012
Create login page & data extraction - LinkedIn 6/9/2012 14/9/2012 Create login page & data extraction - LinkedIn 4/9/2012 18/9/2012 Incomplete.
Team had decided to drop this function, due to the complexity of unable to retrieve the ideal information of (user's work experience, education etc).
Create send email page for external parties 15/9/2012 20/9/2012 Create send email page for external parties - - Task was postponed to Iteration 6.
Create tagging function 18/9/2012 23/9/2012 Create tagging function - - Due to the wide scope of project, team had decided to change the 'Tagging & Filtering' function to a basic 'Search' function that will be implemented in Iteration 7 (After Mid-Term).
Compilation of UT 1 result 22/9/2012 23/9/2012 Create tagging function 22/9/2012 26/9/2012
6 Create send email page for external parties 26/9/2012 30/9/2012 Create send email page for external parties 26/9/2012 4/10/2012
Create filter function 24/9/2012 30/9/2012 Create filter function - - (As explained above) Team had decided to change the 'Tagging & Filtering' function to a basic 'Search' function that will be implemented in Iteration 7 (After Mid-Term).
Final testing & debugging 3/10/2012 5/10/2012 Create send email page for external parties 3/10/2012 7/10/2012
Prepare slides for mid-term presentation 29/9/2012 2/10/2012 Create send email page for external parties 2/10/2012 7/10/2012