Details

Start Date     01 Sep 2011
End Date     23 Oct 2011
Bug KM     <<<View Bug Tracking Log>>>


Iteration Review

  • Discussion to define the scope and detailed requirements of the Project redSpot
  • Develop first version of Use Case diagram to determine the functionalities of the project
  • Discovered that phoneGap has compatibility issues with iOS as it does not support iOS version 4.3 onwards. Informed and discussed with clients and arrived at the decision that the team will continue using phoneGap and wait for further development released till Dec 11