HeaderSIS.jpg

IS480 Team wiki: 2011T2 redSpot Milestones

From IS480
Jump to navigation Jump to search

IS480 Milestones

IS480 Milestones
No. Date Description Deliverables Status
1.
24.10.11
FYP Proposal Submission
  • Provides a resonable scope of project and the deliverables to be accomplished by the team.
Completed
2.
15.12.11
FYP Acceptance Presentation
  • Provide and present an update to Course Coordinator, Supervisor and Sponsors the state of projects, our confidence level of accomplishing the projects and lesson learnt thus far.
Completed
3.
09.01.12
FYP Registration
  • Attend the ONLY lesson for IS480 and give a one-minute pitch on what redSpot is.
Completed
4.
20.02.12
FYP Mid-Term Review Presentation
  • Provide and present an update to the reviewer(s) the state of projects and lesson learnt thus far.
Completed
5.
02.04.12
FYP Poster Submission
  • Submit a poster that provides an overview of Project redSpot at a glance.
Completed
6.
16.04.12
FYP Final Presentation
  • Provide and present to the reviewer(s) the final state of projects, the learning journey and takeaways for IS480.
7.
23.04.12
FYP Poster Exhibition
  • Share with fellow SMU Communities and external participants on what redSpot is all about.

redSpot Milestones

redSpot's Milestones
No. Proposed Date Description Deliverables Status
1.
14.10.11
Design Review Evaluation Provide the followings details to the clients so as to review the scope and requirements of the project:
  • Navigation Flow Diagram
  • Use-Case Diagram
Completed
2.
21.10.11
Design Acceptance Provide a proposal that includes the following:
  • Platform that the application will be deployed
  • List of proposed functionalities
Completed
3.
14.02.12 to 15.02.12
Heuristic Evaluation & User Acceptance Test 1
  1. Provide a UI(or mock-up) for both Administrator and User Applications so as to gather the feedbacks and comments on the design and layout.
    • Plan A: Heurisitc Evaluation will be carried out with the actual users (students of MGMT304).
    • Plan B: Heuristic Evaluation will be carried out with invited participants.
  2. Provide for both Administrator and User Applications with a list of functions(to be determined) to test so as to gather inputs on the usability of the application, and also an opportunities again to gather the feedback on the design and layout after the improvement gathered from Heuristic Evaluation.
Completed
4.
29.03.12
User Acceptance Test 2

Provide for both Administrator and User Applications with a complete list of functions to test so as to gather inputs on the usabilty of the application and possible bugs that the project team might have missed out.

Completed

<< Back to Previous Page | Sitemap