Project Schedule(Planned Schedule Vs Actual Schedule)
Iteration | Schedule Period | Actual Period | Remarks |
Iteration 1 | 1 Nov 2010 - 11 Nov 2010 | 1 Nov 2010 - 11 Nov 2010 | NIL |
Iteration 2 | 8 Nov 2010 - 25 Nov 2010 | 8 Nov 2010 - 25 Nov 2010 | The Speech Recognition function (for web) is completed on 8 Jan 2011. |
Iteration 3 | 26 Nov 2010 - 3 Dec 2010 | 26 Nov 2010 - 17 Dec 2010 | The team will "update" the User Interface/Learning Dashboard if we have the time. |
Iteration 4 | 6 Dec 2010 - 17 Dec 2010 | 13 Dec 2010 - 19 Dec 2010 | NIL |
Iteration 5 | 27 Dec 2010 - 5 Jan 2011 | 10 Jan 2011 - 25 Jan 2011 | NIL |
Iteration 6 | 6 Jan 2011 - 20 Jan 2011 | 26 Jan 2011 - 10 Feb 2011 | NIL |
Iteration 7 | 31 Jan 2011 - 11 Feb 2011 | 11 Feb 2011 - 17 Feb 2011 | NIL |
Iteration 8 | 18 Feb 2011 - 1 Mar 2011 | 17 Feb 2011 - 12 Mar 2011 | NIL |
Iteration 9 | 2 Mar 2011 - 11 Mar 2011 | 2 Mar 2011 - 13 Mar 2011 | NIL |
Functions | Schedule Period | Actual Period | Remarks |
Speech Recognition | 8 Nov 2010 - 25 Nov 2010 | 8 Nov 2010 - 20 Nov 2010 (for console) | This function (for web) is completed on 8 Jan 2011. |
Pre-assignment | 8 Nov 2010 - 25 Nov 2010 | 9 Nov 2010 - 20 Nov 2010 | NIL |
User Interface | 26 Nov 2010 - 3 Dec 2010 | 14 Dec 2010 - 17 Dec 2010 | The team will "update" the User Interface if we have the time. |
Learning Dashboard | 26 Nov 2010 - 3 Dec 2010 | 26 Nov 2010 - 2 Dec 2010 | The team will "update" the Learning Dashboard if we have the time. |
Text Association | 6 Dec 2010 - 14 Dec 2010 | 13 Dec 2010 - 19 Dec 2010 | There is a slight delay in the schedule. |
Basic Functions | 6 Dec 2010 - 14 Dec 2010 | 13 Dec 2010 - 19 Dec 2010 | There is a slight delay in the schedule. |
Cleanup of Code | 20 Dec 2010 - 23 Dec 2010 | 21 Dec 2010 - 24 Dec 2010 | NIL |
Content Development | 27 Dec 2010 - 5 Jan 2011 | 10 Jan 2011 - 25 Jan 2011 | The duration extend as the team meets up with the new lcient and make changes to the entire content based on what the client wants. |
Grammar Capability | 27 Dec 2010 - 5 Jan 2011 | 10 Jan 2011 - 14 Jan 2011 | There is a slight delay in the schedule |
Resource Functions | 6 Jan 2011 - 20 Jan 2011 | 26 Jan 2011 - 10 Feb 2011 | NIL |
User Profile Functions | 6 Jan 2011 - 20 Jan 2011 | 26 Jan 2011 - 10 Feb 2011 | NIL
|
User Interface & Learning Dashboard Redesign | 31 Jan 2011 - 11 Feb 2011 | 11 Feb 2011 - 17 Feb 2011 | NIL |
Convert Questions to PDF & download function (additional function) | 18 Feb 2011 - 1 Mar 2011 | 17 Feb 2011 - 21 Feb 2011 | NIL |
Game (additional function) | 18 Feb 2011 - 1 Mar 2011 | 17 Feb 2011 - 12 Mar 2011 | NIL |