Planned | Actual | |||||
---|---|---|---|---|---|---|
Activity | Start Date | End Date | Activity | Start Date | End Date | Comments |
Iteration 4: Complete Business Functions | 3 Oct 2010 | 9 Oct 2010 | Iteration 4: Complete Business Functions | 3 Oct 2010 | 10 Oct 2010 | Required an extra day for debugging |
Buffer | 10 Oct 2010 | 12 Oct 2010 | Integration and Testing | 10 Oct 2010 | 12 Oct 2010 | Completed development with buffer to spare. Moved Integration and Testing up from next activity block |
Integration and Testing | 13 Oct 2010 | 15 Oct 2010 | Client Testing | 13 Oct 2010 | 13 Oct 2010 | Completed Integration and Testing ahead of time. Able to arrange for and conduct Client Functionality Testing on 13 Oct. |
System Review | 14 Oct 2010 | 14 Oct 2010 | Discussion to review possible feature enhancements in the context of our system architecture. | |||
Iteration 5: Complete Web & Analytics | 16 Oct 2010 | 20 Oct 2010 | Iteration 5: Client Feedback | 15 Oct 2010 | 16 Oct 2010 | Pushed back Iteration 5 to work on enhancements based on feedback from functionality testing |
Planned | Actual | |||||
Activity | Start Date | End Date | Activity | Start Date | End Date | Comments |
Integration and Testing and Preparation for Usability Tests | 17 Oct 2010 | 19 Oct 2010 | Added Integration and Testing of changes from client feedback. Created scripts and routine for broader usability testing. | |||
Buffer | 21 Oct 2010 | 23 Oct 2010 | Iteration 6: Complete Web & Analytics | 20 Oct 2010 | 22 Oct 2010 | Complete Iteration previously postponed (see above) |
Integration and Testing | 23 Oct 2010 | 23 Oct 2010 | Integration and Testing for Web & Analytics features | |||
Soft Launch (Testing with Scientists / IRRI) | 24 Oct 2010 | 27 Oct 2010 | Usability Test #1 | 24 Oct 2010 | 26 Oct 2010 | Completed functionality test with IRRI previously. Switched to doing a blind usability test instead. |
Changes based on feedback from Soft Launch | 28 Oct 2010 | 30 Oct 2010 | Iteration 7: Usability & Interface Enhancements | 27 Oct 2010 | 30 Oct 2010 | Activities have similar aims |
Planned | Actual | |||||
Activity | Start Date | End Date | Activity | Start Date | End Date | Comments |
Buffer | 31 Oct 2010 | 7 Nov 2010 | Prep for remote testing by IRRI (Philippines technical team) | 31 Oct 2010 | 1 Nov 2010 | Managed to secure opportunity to do functional and usability testing with IRRI's technical team in Philippines. Took this time to prepare use cases and screen casts |
Remote testing by IRRI (Philippines technical team) | 2 Nov 2010 | 4 Nov 2010 | Functionality and usability testing of all major functionality via the Internet | |||
Client Feedback | 5 Nov 2010 | 5 Nov 2010 | Teleconference with the Philippines technical team to discuss their thoughts from the remote testing | |||
System Review & Poster | 6 Nov 2010 | 7 Nov 2010 | Teleconference with the Philippines technical team to discuss their thoughts from the remote testing | |||
Final Integration and Testing | 8 Nov 2010 | 10 Nov 2010 | Iteration 7: Implement New UI | 8 Nov 2010 | 9 Nov 2010 | Delayed Final Integration and Testing to implement new UI enhancements based on prior functional and usability tests |
Planned | Actual | |||||
Activity | Start Date | End Date | Activity | Start Date | End Date | Comments |
Buffer | 11 Nov 2010 | 14 Nov 2010 | Integration and Prep for Usability Test #2 | 10 Nov 2010 | 11 Nov 2010 | Test for new UI enhancements and prepare for next round of usability tests |
Usability Test #2 | 12 Nov 2010 | 15 Nov 2010 | Test if new UI enhancements have improved usability, and look out for further opportunities to enhance usability. | |||
Rehearsal | 15 Nov 2010 | 17 Nov 2010 | Iteration 7: Usability Enhancements | 16 Nov 2010 | 17 Nov 2010 | Postpone rehearsal for final presentation to pursue additional opportunities for usability enhancements (from Usability Test #2). |
Buffer | 18 Nov 2010 | 20 Nov 2010 | Final Integration and Testing | 18 Nov 2010 | 20 Nov 2010 | Final rounds of tests to ensure that product is completely ready for deployment. |