Planned Actual
Activity Start Date End Date Activity Start Date End Date Comments
Iteration 4: Complete Business Functions 3 Oct 2010 9 Oct 2010 Iteration 4: Complete Business Functions 3 Oct 2010 10 Oct 2010 Required an extra day for debugging
Buffer 10 Oct 2010 12 Oct 2010 Integration and Testing 10 Oct 2010 12 Oct 2010 Completed development with buffer to spare. Moved Integration and Testing up from next activity block
Integration and Testing 13 Oct 2010 15 Oct 2010 Client Testing 13 Oct 2010 13 Oct 2010 Completed Integration and Testing ahead of time. Able to arrange for and conduct Client Functionality Testing on 13 Oct.
System Review 14 Oct 2010 14 Oct 2010 Discussion to review possible feature enhancements in the context of our system architecture.
Iteration 5: Complete Web & Analytics 16 Oct 2010 20 Oct 2010 Iteration 5: Client Feedback 15 Oct 2010 16 Oct 2010 Pushed back Iteration 5 to work on enhancements based on feedback from functionality testing
Planned Actual
Activity Start Date End Date Activity Start Date End Date Comments
Integration and Testing and Preparation for Usability Tests 17 Oct 2010 19 Oct 2010 Added Integration and Testing of changes from client feedback. Created scripts and routine for broader usability testing.
Buffer 21 Oct 2010 23 Oct 2010 Iteration 6: Complete Web & Analytics 20 Oct 2010 22 Oct 2010 Complete Iteration previously postponed (see above)
Integration and Testing 23 Oct 2010 23 Oct 2010 Integration and Testing for Web & Analytics features
Soft Launch (Testing with Scientists / IRRI) 24 Oct 2010 27 Oct 2010 Usability Test #1 24 Oct 2010 26 Oct 2010 Completed functionality test with IRRI previously. Switched to doing a blind usability test instead.
Changes based on feedback from Soft Launch 28 Oct 2010 30 Oct 2010 Iteration 7: Usability & Interface Enhancements 27 Oct 2010 30 Oct 2010 Activities have similar aims
Planned Actual
Activity Start Date End Date Activity Start Date End Date Comments
Buffer 31 Oct 2010 7 Nov 2010 Prep for remote testing by IRRI (Philippines technical team) 31 Oct 2010 1 Nov 2010 Managed to secure opportunity to do functional and usability testing with IRRI's technical team in Philippines. Took this time to prepare use cases and screen casts
Remote testing by IRRI (Philippines technical team) 2 Nov 2010 4 Nov 2010 Functionality and usability testing of all major functionality via the Internet
Client Feedback 5 Nov 2010 5 Nov 2010 Teleconference with the Philippines technical team to discuss their thoughts from the remote testing
System Review & Poster 6 Nov 2010 7 Nov 2010 Teleconference with the Philippines technical team to discuss their thoughts from the remote testing
Final Integration and Testing 8 Nov 2010 10 Nov 2010 Iteration 7: Implement New UI 8 Nov 2010 9 Nov 2010 Delayed Final Integration and Testing to implement new UI enhancements based on prior functional and usability tests
Planned Actual
Activity Start Date End Date Activity Start Date End Date Comments
Buffer 11 Nov 2010 14 Nov 2010 Integration and Prep for Usability Test #2 10 Nov 2010 11 Nov 2010 Test for new UI enhancements and prepare for next round of usability tests
Usability Test #2 12 Nov 2010 15 Nov 2010 Test if new UI enhancements have improved usability, and look out for further opportunities to enhance usability.
Rehearsal 15 Nov 2010 17 Nov 2010 Iteration 7: Usability Enhancements 16 Nov 2010 17 Nov 2010 Postpone rehearsal for final presentation to pursue additional opportunities for usability enhancements (from Usability Test #2).
Buffer 18 Nov 2010 20 Nov 2010 Final Integration and Testing 18 Nov 2010 20 Nov 2010 Final rounds of tests to ensure that product is completely ready for deployment.