Project Schedule Breakdown

This layer will help you understand our project schedule. We have a total of 6 iterations which started on 26 April 2010 and ending on 22 November 2010. After the iteration, we did a redistribution of modules to better manage and handle the project.

Key modules:

  • Supplier & 
Product
 Management 
Module
  • Inventory 
Tracking 
Module
  • Product Overview Management
  • Warehouse Grid and Inventory Maximization
  • Warehouse Grid and Inventory Optimization
  • Warehouse Grid Constraint

Schedule Update (After Acceptance)

Changes to iteration.png

Schedule Update (After Midterm)

Change to iteration after mid.png


Project Milestone and Schedule

Iteration Modules/Deliverable Planned Actual Status Comments
1 Business Process Analysis 11 Jun 2010 11 Jun 2010 100%
1 Proposal Submission 16 Jun 2010 16 Jun 2010 100%
2 Database Schema Construction 17 Jul 2010 17 Jul 2010 100%
2 Supplier & Product Management Module 30 Jul 2010 30 Jul 2010 100%
2 UAT with sponsor (UAT 1) 2 Aug 2010 2 Aug 2010 100%
3 Project Acceptance Preparation 13 Aug 2010 13 Aug 2010 100%
3 User Management Module 29 Aug 2010 22 Aug 2010 100% -7
3 Inventory Tracking Module 28 Aug 2010 30 Aug 2010 100% 2
3 UAT with sponsor (UAT 2) 1 Sep 2010 1 Sep 2010 100%
3 Warehouse Optimisation Module (Algorithm) 27 Aug 2010 27 Aug 2010 100%
4 Warehouse Optimisation Module (Coding) 19 Sep 2010 24 Sep 2010 100% 5
4 Warehouse Grid Constraint Module (Requirements) 26 Sep 2010 27 Sep 2010 100% 1
5 Midterm Presentation 1 Oct 2010 1 Oct 2010 100%
5 Midterm Report Submission 1 Oct 2010 1 Oct 2010 100%
5 Product Overview Management Module 8 Oct 2010 8 Oct 2010 100%
5 Warehouse Optimisation & Grid Module UI 10 Oct 2010 10 Oct 2010 100%
5 UAT with sponsor (UAT 3) 25 Oct 2010 25 Oct 2010 100%
6 Final Integration and Checks 7 Nov 2010 7 Nov 2010 100%
6 Final UAT with Client (UAT 4) 8 Nov 2010 8 Nov 2010 100%
6 Poster 8 Nov 2010 8 Nov 2010 100%
6 Work on UI changes from Client* 12 Nov 2010 12 Nov 2010 100%
6 Print Function* 18 Nov 2010 18 Nov 2010 100%
6 Final Handover Documentation 19 Nov 2010 19 Nov 2010 100%
6 Final UAT with Changes from Client (UAT 5)* 19 Nov 2010 19 Nov 2010 100%
6 Final Presentation 22 Nov 2010 22 Nov 2010 100%

Additional functions/ things we add in*

Project Schedule (PDF format):

Team Cowabunga Project Schedule CAA 12 Aug 2010
Team Cowabunga Project Schedule CAA 22 Aug 2010
Team Cowabunga Project Schedule CAA 8 Sep 2010
Team Cowabunga Project Schedule CAA 17 Sep 2010
Team Cowabunga Project Schedule CAA 27 Sep 2010
Team Cowabunga Project Schedule CAA 1Oct 2010
Team Cowabunga Project Schedule CAA 8 Oct 2010
Team Cowabunga Project Schedule CAA 8 Nov 2010
Team Cowabunga Project Schedule CAA 15Nov10 2010

Schedule Delay/ Comparison

Comparision.png

From the diagram above, you can see that we were on track during the 1st and 2nd iteration. This is because we were able to make use of the time that we have before the school start to accomplish the task that we have planned for.

However, in iteration 3 and 4 we also learn that there is a need to review the schedule as there were modules that would require more time than others. Therefore changes were made which marks an improvement to the next few iterations. We also decided that we would give more time on the testing of the algorithms and exception cases.