Overview of our project progress
Construction Iteration 1
Week 1 • Design Models & Controller classes and methods • Design/Create database tables
Week 2 • Create Pages and addition controller methods for the functionalities • Begin Documentation of Codes
Week 3 (Milestone: Deliver Manage Admin/Request/Approval for Client Review) • Continue documentation of codes • Testing of various features to make sure no critical bugs • Script Test Run on All 3 Modules • Client presentation
Construction Iteration 2
Week 4 • Make fixes and changes based on client and supervisor feedback • Implement additional features • Implement AJAX interface integration • Design Manage Reporting • Unit Tests for the modules (Class Model)
Week 5 (Milestone: Deliver Manage Reporting/UI for Client Review) • Adding features to the 3 modules • Implement AJAX interface integration • Improve the user interface • Implementing Manage Reporting • Unit Tests for the modules (Interface) • Client presentation
Construction Iteration 3
Week 6 • Make fixes and changes based on client and supervisor feedback (Manage Admin) • Improve the user interface based on feedback from the client • Increase work on Manage Reporting • Ramp up testing for all modules to ready the application for packaging
Week 7 • Finish up Manage Reporting’s features • Tidy up interface issues • Integrate AJAX into Manage Reporting • Focus on testing for all modules • Start creating required client documents • Work on Midterm Reflection
Week 8 (Milestone: Deliver system for client review) • Finalize look and feel, fix all bugs and finish touching up on Manage Reporting • Finish up all testing of all modules • User Acceptance Testing by client • Finalized Midterm Reflection
Project Testing Phase
Week 9 • Automated Black-box Testing for all modules • Prepare for UI testing for feedback
Week 10 • UI testing + Deployment testing • User Documentation
Week 11 (Milestone: Meet with Sponsor) • Preparation for Presentation on 31st Oct • Data/Developer Documentation
Project Deployment Phase
Week 12 • Make changes if any to the system • Preparation for handing over • Poster Design and Implementation
Week 13 • Preparation for handing over • Poster Design and Implementation • Preparation for final presentation
Week 14 • Preparation for handing over • Preparation for final presentation
Week 15 • Preparation for handing over • Preparation for final presentation • Final Presentation • Final Report