Task Metric


Zenith task metric.png


Score TM <= 50 50 < TM <= 75 75 < TM <= 125 125 < TM <= 150 150 > TM
Action 1. Inform supervisor within 24 hours.
2. Re-estimate tasks for future iterations.
3. Consider dropping Tasks.
1. Re-estimate tasks for future iterations.
2. Deduct number of days behind from buffer days.
3. If there are no more buffer days, decide the functionalities to drop.
1. Our estimates are fairly accurate, and are roughly on track.
2. Add/deduct number of days ahead / behind from buffer days.
1. Re-estimate tasks for future iterations.
2. Add number of days ahead to buffer days.
1. Inform supervisor within 24 hours.
2. Re-estimate tasks for future iterations.

Bug Metric

Zenith bug count.png


Zenith bug score.png

Note: There are no coding tasks in iteration 1


Severity Low Impact High Impact Critical Impact
Description User interface display errors, such as out of alignment, colour used is not according to theme.

It does not affect the functionality of the system.

The system is functional with some non-critical functionalities are not working. The system is not functional.

Bugs have to be fixed before proceeding.


Points BM <= 5 5 < BM < 10 BM >= 10
Description The system does not need immediate fixing, could be fixed during buffer time or during coding sessions Coders to use planned debugging time in the iteration to solve the bug The team has to stop all current development and resolve the bug immediately