Qui Vivra Verra - Risk Management

From Analytics Practicum
Revision as of 23:26, 10 October 2016 by Cxpong.2013 (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search



  HOME

  ABOUT US

  PROJECT OVERVIEW

  PROJECT FINDINGS

  PROJECT MANAGEMENT

  DOCUMENTATION



Risk Management Table
Risks & Limitations Mitigation Strategy
Lack of experience with analytical tools (i.e. Apache Spark, SpatiaLite, JMP Pro 12)
Explore and familiarize with the tools prior to using them to perform the actual analyses. Use the week before iteration one as the study week to learn the necessary skills required to wield the tools.
Changes in work schedule due to unexpected events; delay of first release and other milestones
Raise awareness about the change and re-look the work breakdown structure and tasks allocation.
Presence of other projects that will potentially hinder the project progress
Priority of this project is emphasized. The introduction of a buffer week will also help to reduce the associated impact.