Difference between revisions of "ANLY482 AY2017-18T2 Group03 Project Management"
Jump to navigation
Jump to search
Line 58: | Line 58: | ||
• Find a way to calculate the amount of workers and total overtime hours needed in order to satisfy the order requirement for any day.<br/> | • Find a way to calculate the amount of workers and total overtime hours needed in order to satisfy the order requirement for any day.<br/> | ||
</td> | </td> | ||
− | <td | + | <td>As there was no way for them to provide us with information on the time taken taken to complete each task, we would have no way to come up with the model to derive the number of workers required for the amount of workload provided. On top of that, they were unable to provide us with the number of hours worked for each worker and which day the worker actually worked, making it almost impossible to link their individual performance to actual work completed. |
+ | </td> | ||
+ | <td> | ||
+ | * Discuss with sponsor immediately to see if they can provide us with a new data set in order to carry on with the project. | ||
+ | * <b>Russell</b> to follow up. | ||
</td> | </td> | ||
− | |||
<td>Complete as of 26th January</td> | <td>Complete as of 26th January</td> | ||
</tr> | </tr> |
Revision as of 00:08, 12 February 2018
HOME | ABOUT US | PROJECT OVERVIEW | DATA ANALYSIS | PROJECT MANAGEMENT | DOCUMENTATION | MAIN PAGE |
Previous | Current |
---|
Project Management
Change Management
Sponsor Requirement Change Log | |||||||
---|---|---|---|---|---|---|---|
Date | Milestones | Dataset | Feature Requirement (Before) | Feature Requirement (After) | Status | Status Description | |
20th Jan | Post project Proposal |
All data were given in excel format
|
• Find a way to calculate the amount of workers and total overtime hours needed in order to satisfy the order requirement for any day. |
As there was no way for them to provide us with information on the time taken taken to complete each task, we would have no way to come up with the model to derive the number of workers required for the amount of workload provided. On top of that, they were unable to provide us with the number of hours worked for each worker and which day the worker actually worked, making it almost impossible to link their individual performance to actual work completed. |
|
Complete as of 26th January | |
31st Jan | Before Project Proposal | All data were given in excel format
|
• Find a way to calculate the amount of workers and total overtime hours needed in order to satisfy the order requirement for any day. |
|
|
NIL |