Difference between revisions of "ANLY482 AY2016-17 T2 Group15 Project Management"

From Analytics Practicum
Jump to navigation Jump to search
 
(15 intermediate revisions by the same user not shown)
Line 1: Line 1:
 +
[[Image:edufy back.png | 48px | link=ANLY482 AY2016-17 Term 2]]
 +
[[ANLY482 AY2016-17 Term 2 | <font color="#000000">Back to Project Main Page</font>]]
 
<center>
 
<center>
 
[[Image:edufy icon.png | link=ANLY482_AY2016-17_T2_Group15]]
 
[[Image:edufy icon.png | link=ANLY482_AY2016-17_T2_Group15]]
Line 33: Line 35:
 
</div>
 
</div>
 
</div>
 
</div>
 +
{| class="wikitable" style="margin: 0 auto; margin-top: 10px;"
 +
|-
 +
! style="background:#424242; color:white"|Tasks
 +
! style="background:#424242; color:white"|Start Week
 +
! style="background:#424242; color:white"|End Week
 +
! style="background:#424242; color:white"|Teammates Involved
 +
! style="background:#424242; color:white"|Status
 +
 +
|- style="background:#9E9E9E; color:white; text-align: left;"
 +
|colspan="5"|'''Project Preparation'''
 +
|-
 +
|-
 +
| Understanding Sponsor Requirements
 +
| Week 0
 +
| Week 1
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Project Acceptance
 +
| Week 0
 +
| Week 1
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Create and Update Wikipedia
 +
| Week 0
 +
| Week 2
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Proposal in Word Document & Wikipedia
 +
| Week 1
 +
| Week 2
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|- style="background:#9E9E9E; color:white; text-align: left;"
 +
|colspan="5"|'''Data Gathering & Scoping'''
 +
|-
 +
|-
 +
| Gather Data
 +
| Week 1
 +
| Week 2
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Finalize Requirements with Sponsor
 +
| Week 1
 +
| Week 2
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Scope Project
 +
| Week 2
 +
| Week 2
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|- style="background:#9E9E9E; color:white; text-align: left;"
 +
|colspan="5"|'''Research & Preparation'''
 +
|-
 +
|-
 +
| Explore Software
 +
| Week 2
 +
| Week 2
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Finalize Proposal
 +
| Week 2
 +
| Week 2
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|- style="background:#9E9E9E; color:white; text-align: left;"
 +
|colspan="5"|'''Data Cleaning'''
 +
|-
 +
| Data Collection
 +
| Week 2
 +
| Week 3
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Data Cleaning
 +
| Week 4
 +
| Week 5
 +
| Kok Chin, Zhan Hao
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Data Transformation
 +
| Week 5
 +
| Week 5
 +
| Alson
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|- style="background:#9E9E9E; color:white; text-align: left;"
 +
|colspan="5"|'''Data Modeling'''
 +
|-
 +
|-
 +
| Exploratory Analysis
 +
| Week 6
 +
| Week 7
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|- style="background:#9E9E9E; color:white; text-align: left;"
 +
|colspan="5"|'''Interim Preparation'''
 +
|-
 +
|-
 +
| Gather Feedback from Sponsor
 +
| Week 7
 +
| Week 7
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Prepare Interim Report & Slides
 +
| Week 7
 +
| Week 7
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Buffer
 +
| Week 7
 +
| Week 8
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|- style="background:#9E9E9E; color:white; text-align: left;"
 +
|colspan="5"|'''Application Building'''
 +
|-
 +
|-
 +
| Learn R
 +
| Week 9
 +
| Week 10
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Build R Model (Iteration 1)
 +
| Week 9
 +
| Week 10
 +
| Kok Chin, Zhan Hao
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Refine Analysis After Interim
 +
| Week 9
 +
| Week 10
 +
| Alson, Zhan Hao
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Improve R Model (Iteration 2)
 +
| Week 11
 +
| Week 11
 +
| Kok Chin
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Gather Feedback from Sponsor
 +
| Week 12
 +
| Week 12
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Build R Model (Iteration 3)
 +
| Week 12
 +
| Week 12
 +
| Kok Chin
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Buffer
 +
| Week 12
 +
| Week 12
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|- style="background:#9E9E9E; color:white; text-align: left;"
 +
|colspan="5"|'''Final Preparation'''
 +
|-
 +
|-
 +
| Adjust Analysis
 +
| Week 13
 +
| Week 14
 +
| Alson
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Improve R Model (Final Iteration)
 +
| Week 14
 +
| Week 15
 +
| Kok Chin
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Finalize Conference Paper
 +
| Week 15
 +
| Week 16
 +
| Zhan Hao
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|-
 +
|-
 +
| Finalize Poster
 +
| Week 15
 +
| Week 16
 +
| All
 +
| style="background:#2E7D32; color:white"| <center>'''Completed'''</center>
 +
|}
  
  

Latest revision as of 11:03, 21 April 2017

Edufy back.png Back to Project Main Page

Edufy icon.png

Edufy homeicon.png Home

Edufy projectoverviewicon.png Project Overview

Edufy analysisicon.png Analysis & Findings

Edufy projectmanagementicon.png Project Management

Edufy documentationicon.png Documentation


Project Timeline
Tasks Start Week End Week Teammates Involved Status
Project Preparation
Understanding Sponsor Requirements Week 0 Week 1 All
Completed
Project Acceptance Week 0 Week 1 All
Completed
Create and Update Wikipedia Week 0 Week 2 All
Completed
Proposal in Word Document & Wikipedia Week 1 Week 2 All
Completed
Data Gathering & Scoping
Gather Data Week 1 Week 2 All
Completed
Finalize Requirements with Sponsor Week 1 Week 2 All
Completed
Scope Project Week 2 Week 2 All
Completed
Research & Preparation
Explore Software Week 2 Week 2 All
Completed
Finalize Proposal Week 2 Week 2 All
Completed
Data Cleaning
Data Collection Week 2 Week 3 All
Completed
Data Cleaning Week 4 Week 5 Kok Chin, Zhan Hao
Completed
Data Transformation Week 5 Week 5 Alson
Completed
Data Modeling
Exploratory Analysis Week 6 Week 7 All
Completed
Interim Preparation
Gather Feedback from Sponsor Week 7 Week 7 All
Completed
Prepare Interim Report & Slides Week 7 Week 7 All
Completed
Buffer Week 7 Week 8 All
Completed
Application Building
Learn R Week 9 Week 10 All
Completed
Build R Model (Iteration 1) Week 9 Week 10 Kok Chin, Zhan Hao
Completed
Refine Analysis After Interim Week 9 Week 10 Alson, Zhan Hao
Completed
Improve R Model (Iteration 2) Week 11 Week 11 Kok Chin
Completed
Gather Feedback from Sponsor Week 12 Week 12 All
Completed
Build R Model (Iteration 3) Week 12 Week 12 Kok Chin
Completed
Buffer Week 12 Week 12 All
Completed
Final Preparation
Adjust Analysis Week 13 Week 14 Alson
Completed
Improve R Model (Final Iteration) Week 14 Week 15 Kok Chin
Completed
Finalize Conference Paper Week 15 Week 16 Zhan Hao
Completed
Finalize Poster Week 15 Week 16 All
Completed


Gantt Chart

Edufy ganttchart.png Edufy legend.png