Difference between revisions of "ANLY482 AY2016-17 T2 Group15 Project Management"
Jump to navigation
Jump to search
Kcheng.2013 (talk | contribs) |
Kcheng.2013 (talk | contribs) |
||
(15 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
+ | [[Image:edufy back.png | 48px | link=ANLY482 AY2016-17 Term 2]] | ||
+ | [[ANLY482 AY2016-17 Term 2 | <font color="#000000">Back to Project Main Page</font>]] | ||
<center> | <center> | ||
[[Image:edufy icon.png | link=ANLY482_AY2016-17_T2_Group15]] | [[Image:edufy icon.png | link=ANLY482_AY2016-17_T2_Group15]] | ||
Line 33: | Line 35: | ||
</div> | </div> | ||
</div> | </div> | ||
+ | {| class="wikitable" style="margin: 0 auto; margin-top: 10px;" | ||
+ | |- | ||
+ | ! style="background:#424242; color:white"|Tasks | ||
+ | ! style="background:#424242; color:white"|Start Week | ||
+ | ! style="background:#424242; color:white"|End Week | ||
+ | ! style="background:#424242; color:white"|Teammates Involved | ||
+ | ! style="background:#424242; color:white"|Status | ||
+ | |||
+ | |- style="background:#9E9E9E; color:white; text-align: left;" | ||
+ | |colspan="5"|'''Project Preparation''' | ||
+ | |- | ||
+ | |- | ||
+ | | Understanding Sponsor Requirements | ||
+ | | Week 0 | ||
+ | | Week 1 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Project Acceptance | ||
+ | | Week 0 | ||
+ | | Week 1 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Create and Update Wikipedia | ||
+ | | Week 0 | ||
+ | | Week 2 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Proposal in Word Document & Wikipedia | ||
+ | | Week 1 | ||
+ | | Week 2 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- style="background:#9E9E9E; color:white; text-align: left;" | ||
+ | |colspan="5"|'''Data Gathering & Scoping''' | ||
+ | |- | ||
+ | |- | ||
+ | | Gather Data | ||
+ | | Week 1 | ||
+ | | Week 2 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Finalize Requirements with Sponsor | ||
+ | | Week 1 | ||
+ | | Week 2 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Scope Project | ||
+ | | Week 2 | ||
+ | | Week 2 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- style="background:#9E9E9E; color:white; text-align: left;" | ||
+ | |colspan="5"|'''Research & Preparation''' | ||
+ | |- | ||
+ | |- | ||
+ | | Explore Software | ||
+ | | Week 2 | ||
+ | | Week 2 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Finalize Proposal | ||
+ | | Week 2 | ||
+ | | Week 2 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- style="background:#9E9E9E; color:white; text-align: left;" | ||
+ | |colspan="5"|'''Data Cleaning''' | ||
+ | |- | ||
+ | | Data Collection | ||
+ | | Week 2 | ||
+ | | Week 3 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Data Cleaning | ||
+ | | Week 4 | ||
+ | | Week 5 | ||
+ | | Kok Chin, Zhan Hao | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Data Transformation | ||
+ | | Week 5 | ||
+ | | Week 5 | ||
+ | | Alson | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- style="background:#9E9E9E; color:white; text-align: left;" | ||
+ | |colspan="5"|'''Data Modeling''' | ||
+ | |- | ||
+ | |- | ||
+ | | Exploratory Analysis | ||
+ | | Week 6 | ||
+ | | Week 7 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- style="background:#9E9E9E; color:white; text-align: left;" | ||
+ | |colspan="5"|'''Interim Preparation''' | ||
+ | |- | ||
+ | |- | ||
+ | | Gather Feedback from Sponsor | ||
+ | | Week 7 | ||
+ | | Week 7 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Prepare Interim Report & Slides | ||
+ | | Week 7 | ||
+ | | Week 7 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Buffer | ||
+ | | Week 7 | ||
+ | | Week 8 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- style="background:#9E9E9E; color:white; text-align: left;" | ||
+ | |colspan="5"|'''Application Building''' | ||
+ | |- | ||
+ | |- | ||
+ | | Learn R | ||
+ | | Week 9 | ||
+ | | Week 10 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Build R Model (Iteration 1) | ||
+ | | Week 9 | ||
+ | | Week 10 | ||
+ | | Kok Chin, Zhan Hao | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Refine Analysis After Interim | ||
+ | | Week 9 | ||
+ | | Week 10 | ||
+ | | Alson, Zhan Hao | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Improve R Model (Iteration 2) | ||
+ | | Week 11 | ||
+ | | Week 11 | ||
+ | | Kok Chin | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Gather Feedback from Sponsor | ||
+ | | Week 12 | ||
+ | | Week 12 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Build R Model (Iteration 3) | ||
+ | | Week 12 | ||
+ | | Week 12 | ||
+ | | Kok Chin | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Buffer | ||
+ | | Week 12 | ||
+ | | Week 12 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- style="background:#9E9E9E; color:white; text-align: left;" | ||
+ | |colspan="5"|'''Final Preparation''' | ||
+ | |- | ||
+ | |- | ||
+ | | Adjust Analysis | ||
+ | | Week 13 | ||
+ | | Week 14 | ||
+ | | Alson | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Improve R Model (Final Iteration) | ||
+ | | Week 14 | ||
+ | | Week 15 | ||
+ | | Kok Chin | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Finalize Conference Paper | ||
+ | | Week 15 | ||
+ | | Week 16 | ||
+ | | Zhan Hao | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |- | ||
+ | |- | ||
+ | | Finalize Poster | ||
+ | | Week 15 | ||
+ | | Week 16 | ||
+ | | All | ||
+ | | style="background:#2E7D32; color:white"| <center>'''Completed'''</center> | ||
+ | |} | ||
Latest revision as of 11:03, 21 April 2017
Project Timeline
Tasks | Start Week | End Week | Teammates Involved | Status |
---|---|---|---|---|
Project Preparation | ||||
Understanding Sponsor Requirements | Week 0 | Week 1 | All | |
Project Acceptance | Week 0 | Week 1 | All | |
Create and Update Wikipedia | Week 0 | Week 2 | All | |
Proposal in Word Document & Wikipedia | Week 1 | Week 2 | All | |
Data Gathering & Scoping | ||||
Gather Data | Week 1 | Week 2 | All | |
Finalize Requirements with Sponsor | Week 1 | Week 2 | All | |
Scope Project | Week 2 | Week 2 | All | |
Research & Preparation | ||||
Explore Software | Week 2 | Week 2 | All | |
Finalize Proposal | Week 2 | Week 2 | All | |
Data Cleaning | ||||
Data Collection | Week 2 | Week 3 | All | |
Data Cleaning | Week 4 | Week 5 | Kok Chin, Zhan Hao | |
Data Transformation | Week 5 | Week 5 | Alson | |
Data Modeling | ||||
Exploratory Analysis | Week 6 | Week 7 | All | |
Interim Preparation | ||||
Gather Feedback from Sponsor | Week 7 | Week 7 | All | |
Prepare Interim Report & Slides | Week 7 | Week 7 | All | |
Buffer | Week 7 | Week 8 | All | |
Application Building | ||||
Learn R | Week 9 | Week 10 | All | |
Build R Model (Iteration 1) | Week 9 | Week 10 | Kok Chin, Zhan Hao | |
Refine Analysis After Interim | Week 9 | Week 10 | Alson, Zhan Hao | |
Improve R Model (Iteration 2) | Week 11 | Week 11 | Kok Chin | |
Gather Feedback from Sponsor | Week 12 | Week 12 | All | |
Build R Model (Iteration 3) | Week 12 | Week 12 | Kok Chin | |
Buffer | Week 12 | Week 12 | All | |
Final Preparation | ||||
Adjust Analysis | Week 13 | Week 14 | Alson | |
Improve R Model (Final Iteration) | Week 14 | Week 15 | Kok Chin | |
Finalize Conference Paper | Week 15 | Week 16 | Zhan Hao | |
Finalize Poster | Week 15 | Week 16 | All |
Gantt Chart