Risk Metric
Impact / Likelihood | Low | Medium | High |
---|---|---|---|
High | B | A | A |
Medium | C | B | A |
Low | C | C | B |
Risk Assessment
Risk Type & Description | Consequences | Likelihood | Impact | Level | Mitigation |
---|---|---|---|---|---|
Technical Risk Steep learning curve as team are unfamiliar with D3.JS and JMP. |
Project may be delayed due to:
|
High | High | A |
|
Technical Risk Team members have not taken IS428 - Visual Analytics for Business Intelligence (VA) module. |
Team may be unsure of the best practices of information graphics to present data in the language of graphics effectively, clearly and eloquently. | High | Medium | A |
|
Client Management Risk Client may be making frequent changes to the project scope. |
Project may be delayed due to frequent readjustment of project scope and expectation may lead to an over-run in project. | Medium | Medium | B |
|
Project Management Risk There are certain features such as warehouse utilization tool, which the team are unsure of the time needed to complete it. |
Project may be delayed due to incorrect estimation of time can lead to the feature not being completed on time. | Medium | Medium | B |
|