Milestones
| Number |
Milestone |
Planned Start Date |
Planned End Date |
Status |
Mitigation Plan
|
| 1 |
Finalization of topic |
20 Dec 2019 |
3 Jan 2020 |
Completed |
|
| 2 |
Completion of cleaning data |
4 Jan 2020 |
31 Jan 2020 |
Completed |
|
| 3 |
Data Analysis |
1 Feb 2020 |
30 Mar 2020 |
In Progress |
(New) User Profile Analysis
|
| 4 |
Report Finished |
1 April 2020 |
30 Apr 2020 |
In Progress |
|
Project Schedule
| Activity |
Date
|
| Sponsor meeting 1 |
15 Jan 2020
|
| Supervisor meeting 1 |
16 Jan 2020
|
| Wiki page creation |
16 Jan 2020
|
| Read GPS data with Pandas |
20 Jan 2020
|
| Combine data for each user |
27 Jan 2020
|
| Statistical analysis on GPS data |
27 Jan 2020
|
| Sponsor meeting 2 |
29 Jan 2020
|
| Supervisor meeting 2 |
30 Jan 2020
|
| Manually analyze user profile data |
1 Feb 2020
|
| Designed code to automatically analyze user profile data |
2 Feb 2020
|
| Finish analysis of Block 10 user profile data |
3 Feb 2020
|
| Sponsor meeting 3 |
4 Feb 2020
|
| Supervisor meeting 3 |
6 Feb 2020
|
| Sponsor meeting 4 |
11 Feb 2020
|
| Midterm Presentation |
20 Feb 2020
|
| Supervisor meeting 4 |
5 March 2020
|