Yschen.2017 (talk | contribs) |
Yschen.2017 (talk | contribs) |
||
| Line 26: | Line 26: | ||
{| class="wikitable" | {| class="wikitable" | ||
|- | |- | ||
| − | ! Number !! Milestone !! Planned Date !! Status !! Mitigation Plan | + | ! Number !! Milestone !! Planned Start Date !! Planned End Date !! Status !! Mitigation Plan |
|- | |- | ||
| − | | 1 || | + | | 1 || Finalization of topic || 20 Dec 2019 || 3 Jan 2020 || Completed || - |
|- | |- | ||
| − | | 2 || | + | | 2 || Completion of cleaning data || 4 Jan 2020 || 31 Jan 2020 || Completed || - |
|- | |- | ||
| − | | 3 || Data | + | | 3 || Data Analysis || 1 Feb 2020 || 14 Feb 2020 || In Progress || (New) User Profile Analysis |
|- | |- | ||
| − | | 4 || | + | | 4 || Report Finished || 1 April 2020 || 30 Apr 2020 || In Progess || - |
|} | |} | ||
Revision as of 14:29, 30 January 2020
Milestones
| Number | Milestone | Planned Start Date | Planned End Date | Status | Mitigation Plan |
|---|---|---|---|---|---|
| 1 | Finalization of topic | 20 Dec 2019 | 3 Jan 2020 | Completed | - |
| 2 | Completion of cleaning data | 4 Jan 2020 | 31 Jan 2020 | Completed | - |
| 3 | Data Analysis | 1 Feb 2020 | 14 Feb 2020 | In Progress | (New) User Profile Analysis |
| 4 | Report Finished | 1 April 2020 | 30 Apr 2020 | In Progess | - |
Project Schedule
| Activity | Date |
|---|---|
| Sponsor meeting 1 | 15 Jan 2020 |
| Supervisor meeting 1 | 16 Jan 2020 |
| Read GPS data with Pandas | 20 Jan 2020 |
| Combine data for each user | 27 Jan 2020 |
| Statistical analysis on GPS data | 27 Jan 2020 |
| Sponsor meeting 2 | 29 Jan 2020 |
| Supervisor meeting 2 | 30 Jan 2020 |