Difference between revisions of "SMT483G4: WheelGo Project Management"

From SMT Project Experience
Jump to navigation Jump to search
Line 26: Line 26:
 
{| class="wikitable"
 
{| class="wikitable"
 
|-
 
|-
! Number !! Milestone !! Planned Date !! Status !! Mitigation Plan  
+
! Number !! Milestone !! Planned Start Date !! Planned End Date !! Status !! Mitigation Plan  
 
|-
 
|-
| 1 || Proeject Proposal Completion || 3 Jan 2020 || Completed || -
+
| 1 || Finalization of topic || 20 Dec 2019 || 3 Jan 2020 || Completed || -
 
|-
 
|-
| 2 || Project Wiki Page Creation || 15 Jan 2020 || Completed || -  
+
| 2 || Completion of cleaning data || 4 Jan 2020 || 31 Jan 2020 || Completed || -  
 
|-
 
|-
| 3 || Data Cleaning  || 31 Jan 2020 || Completed || -
+
| 3 || Data Analysis || 1 Feb 2020 || 14 Feb 2020 || In Progress || (New) User Profile Analysis
 
|-
 
|-
| 4 || Data Analysis || 14 Feb 2020 || In Progress || (New) User Profile Analysis
+
| 4 || Report Finished || 1 April 2020 || 30 Apr 2020 || In Progess || -
 
|}
 
|}
  

Revision as of 14:29, 30 January 2020

WheelGologo.png

HOME

BACKGROUND

PROJECT OVERVIEW

PROJECT MANAGEMENT

DOCUMENTATION

Milestones

Number Milestone Planned Start Date Planned End Date Status Mitigation Plan
1 Finalization of topic 20 Dec 2019 3 Jan 2020 Completed -
2 Completion of cleaning data 4 Jan 2020 31 Jan 2020 Completed -
3 Data Analysis 1 Feb 2020 14 Feb 2020 In Progress (New) User Profile Analysis
4 Report Finished 1 April 2020 30 Apr 2020 In Progess -

Project Schedule

Activity Date
Sponsor meeting 1 15 Jan 2020
Supervisor meeting 1 16 Jan 2020
Read GPS data with Pandas 20 Jan 2020
Combine data for each user 27 Jan 2020
Statistical analysis on GPS data 27 Jan 2020
Sponsor meeting 2 29 Jan 2020
Supervisor meeting 2 30 Jan 2020