Revision as of 14:22, 30 January 2020
Milestones
| Number | Milestone | Planned Date | Status | Mitigation Plan |
|---|---|---|---|---|
| 1 | Proeject Proposal Completion | 3 Jan 2020 | Completed | - |
| 2 | Project Wiki Page Creation | 15 Jan 2020 | Completed | - |
| 3 | Data Cleaning | 31 Jan 2020 | Completed | - |
| 4 | Data Analysis | 14 Feb 2020 | In Progress | (New) User Profile Analysis |
Project Schedule
| Activity | Date |
|---|---|
| Sponsor meeting 1 | 15 Jan 2020 |
| Supervisor meeting 1 | 16 Jan 2020 |
| Read GPS data with Pandas | 20 Jan 2020 |
| Combine data for each user | 27 Jan 2020 |
| Statistical analysis on GPS data | 27 Jan 2020 |
| Sponsor meeting 2 | 29 Jan 2020 |
| Supervisor meeting 2 | 30 Jan 2020 |