Difference between revisions of "SMT483G4: WheelGo Project Management"
Jump to navigation
Jump to search
Yschen.2017 (talk | contribs) |
Yschen.2017 (talk | contribs) |
||
Line 34: | Line 34: | ||
| 3 || Data Cleaning || 31 Jan 2020 || Completed || - | | 3 || Data Cleaning || 31 Jan 2020 || Completed || - | ||
|- | |- | ||
− | | 4 || | + | | 4 || Data Analysis || 14 Feb 2020 || In Progress || (New) User Profile Analysis |
|} | |} | ||
Revision as of 14:22, 30 January 2020
Milestones
Number | Milestone | Planned Date | Status | Mitigation Plan |
---|---|---|---|---|
1 | Proeject Proposal Completion | 3 Jan 2020 | Completed | - |
2 | Project Wiki Page Creation | 15 Jan 2020 | Completed | - |
3 | Data Cleaning | 31 Jan 2020 | Completed | - |
4 | Data Analysis | 14 Feb 2020 | In Progress | (New) User Profile Analysis |
Project Schedule
Activity | Date |
---|---|
Sponsor meeting 1 | 15 Jan 2020 |
Supervisor meeting 1 | 16 Jan 2020 |
Read GPS data with Pandas | 20 Jan 2020 |
Combine data for each user | 27 Jan 2020 |
Statistical analysis on GPS data | 27 Jan 2020 |
Sponsor meeting 2 | 29 Jan 2020 |
Supervisor meeting 2 | 30 Jan 2020 |