Difference between revisions of "SMT483G4: WheelGo Project Management"
Jump to navigation
Jump to search
Yschen.2017 (talk | contribs) |
Yschen.2017 (talk | contribs) |
||
(10 intermediate revisions by the same user not shown) | |||
Line 26: | Line 26: | ||
{| class="wikitable" | {| class="wikitable" | ||
|- | |- | ||
− | ! Number !! Milestone !! Planned Date !! Status !! Mitigation Plan | + | ! Number !! Milestone !! Planned Start Date !! Planned End Date !! Status !! Mitigation Plan |
|- | |- | ||
− | | 1 || | + | | 1 || Finalization of topic || 20 Dec 2019 || 3 Jan 2020 || Completed || |
|- | |- | ||
− | | 2 || | + | | 2 || Completion of cleaning data || 4 Jan 2020 || 31 Jan 2020 || Completed || |
|- | |- | ||
− | | 3 || Data | + | | 3 || Data Analysis || 1 Feb 2020 || 30 Mar 2020 || In Progress || (New) User Profile Analysis |
|- | |- | ||
− | | 4 || | + | | 4 || Report Finished || 1 April 2020 || 30 Apr 2020 || In Progress || |
|} | |} | ||
Line 45: | Line 45: | ||
|- | |- | ||
| Supervisor meeting 1 || 16 Jan 2020 | | Supervisor meeting 1 || 16 Jan 2020 | ||
+ | |- | ||
+ | | Wiki page creation || 16 Jan 2020 | ||
|- | |- | ||
| Read GPS data with Pandas || 20 Jan 2020 | | Read GPS data with Pandas || 20 Jan 2020 | ||
Line 55: | Line 57: | ||
|- | |- | ||
| Supervisor meeting 2 || 30 Jan 2020 | | Supervisor meeting 2 || 30 Jan 2020 | ||
+ | |- | ||
+ | | Manually analyze user profile data || 1 Feb 2020 | ||
+ | |- | ||
+ | | Designed code to automatically analyze user profile data || 2 Feb 2020 | ||
+ | |- | ||
+ | | Finish analysis of Block 10 user profile data || 3 Feb 2020 | ||
+ | |- | ||
+ | | Sponsor meeting 3 || 4 Feb 2020 | ||
+ | |- | ||
+ | | Supervisor meeting 3 || 6 Feb 2020 | ||
+ | |- | ||
+ | | Sponsor meeting 4 || 11 Feb 2020 | ||
+ | |- | ||
+ | | Midterm Presentation || 20 Feb 2020 | ||
+ | |- | ||
+ | | Route Analysis || 3 Mar 2020 | ||
+ | |- | ||
+ | | Supervisor meeting 4 || 5 Mar 2020 | ||
+ | |- | ||
+ | | Route Analysis - Testing|| 10 Mar 2020 | ||
|} | |} |
Latest revision as of 17:43, 15 March 2020
Milestones
Number | Milestone | Planned Start Date | Planned End Date | Status | Mitigation Plan |
---|---|---|---|---|---|
1 | Finalization of topic | 20 Dec 2019 | 3 Jan 2020 | Completed | |
2 | Completion of cleaning data | 4 Jan 2020 | 31 Jan 2020 | Completed | |
3 | Data Analysis | 1 Feb 2020 | 30 Mar 2020 | In Progress | (New) User Profile Analysis |
4 | Report Finished | 1 April 2020 | 30 Apr 2020 | In Progress |
Project Schedule
Activity | Date |
---|---|
Sponsor meeting 1 | 15 Jan 2020 |
Supervisor meeting 1 | 16 Jan 2020 |
Wiki page creation | 16 Jan 2020 |
Read GPS data with Pandas | 20 Jan 2020 |
Combine data for each user | 27 Jan 2020 |
Statistical analysis on GPS data | 27 Jan 2020 |
Sponsor meeting 2 | 29 Jan 2020 |
Supervisor meeting 2 | 30 Jan 2020 |
Manually analyze user profile data | 1 Feb 2020 |
Designed code to automatically analyze user profile data | 2 Feb 2020 |
Finish analysis of Block 10 user profile data | 3 Feb 2020 |
Sponsor meeting 3 | 4 Feb 2020 |
Supervisor meeting 3 | 6 Feb 2020 |
Sponsor meeting 4 | 11 Feb 2020 |
Midterm Presentation | 20 Feb 2020 |
Route Analysis | 3 Mar 2020 |
Supervisor meeting 4 | 5 Mar 2020 |
Route Analysis - Testing | 10 Mar 2020 |