Difference between revisions of "SMT483G4: WheelGo Project Management"
Jump to navigation
Jump to search
Yschen.2017 (talk | contribs) |
Yschen.2017 (talk | contribs) |
||
Line 67: | Line 67: | ||
|- | |- | ||
| Sponsor meeting 4 || 11 Feb 2020 | | Sponsor meeting 4 || 11 Feb 2020 | ||
+ | |- | ||
+ | | Midterm Presentation || 20 Feb 2020 | ||
|} | |} |
Revision as of 16:31, 26 February 2020
Milestones
Number | Milestone | Planned Start Date | Planned End Date | Status | Mitigation Plan |
---|---|---|---|---|---|
1 | Finalization of topic | 20 Dec 2019 | 3 Jan 2020 | Completed | |
2 | Completion of cleaning data | 4 Jan 2020 | 31 Jan 2020 | Completed | |
3 | Data Analysis | 1 Feb 2020 | 30 Mar 2020 | In Progress | (New) User Profile Analysis |
4 | Report Finished | 1 April 2020 | 30 Apr 2020 | In Progress |
Project Schedule
Activity | Date |
---|---|
Sponsor meeting 1 | 15 Jan 2020 |
Supervisor meeting 1 | 16 Jan 2020 |
Wiki page creation | 16 Jan 2020 |
Read GPS data with Pandas | 20 Jan 2020 |
Combine data for each user | 27 Jan 2020 |
Statistical analysis on GPS data | 27 Jan 2020 |
Sponsor meeting 2 | 29 Jan 2020 |
Supervisor meeting 2 | 30 Jan 2020 |
Manually analyze user profile data | 1 Feb 2020 |
Designed code to automatically analyze user profile data | 2 Feb 2020 |
Finish analysis of Block 10 user profile data | 3 Feb 2020 |
Sponsor meeting 3 | 4 Feb 2020 |
Sponsor meeting 4 | 11 Feb 2020 |
Midterm Presentation | 20 Feb 2020 |