Difference between revisions of "SMT483G4: WheelGo Project Management"

From SMT Project Experience
Jump to navigation Jump to search
 
(7 intermediate revisions by the same user not shown)
Line 28: Line 28:
 
! Number !! Milestone !! Planned Start Date !! Planned End Date !! Status !! Mitigation Plan  
 
! Number !! Milestone !! Planned Start Date !! Planned End Date !! Status !! Mitigation Plan  
 
|-
 
|-
| 1 || Finalization of topic || 20 Dec 2019 || 3 Jan 2020 || Completed || -
+
| 1 || Finalization of topic || 20 Dec 2019 || 3 Jan 2020 || Completed ||  
 
|-
 
|-
| 2 || Completion of cleaning data || 4 Jan 2020 || 31 Jan 2020 || Completed || -
+
| 2 || Completion of cleaning data || 4 Jan 2020 || 31 Jan 2020 || Completed ||  
 
|-
 
|-
| 3 || Data Analysis || 1 Feb 2020 || 14 Feb 2020 || In Progress || (New) User Profile Analysis  
+
| 3 || Data Analysis || 1 Feb 2020 || 30 Mar 2020 || In Progress || (New) User Profile Analysis  
 
|-
 
|-
| 4 || Report Finished || 1 April 2020 || 30 Apr 2020 || In Progress || -
+
| 4 || Report Finished || 1 April 2020 || 30 Apr 2020 || In Progress ||  
 
|}
 
|}
  
Line 45: Line 45:
 
|-
 
|-
 
| Supervisor meeting 1 || 16 Jan 2020
 
| Supervisor meeting 1 || 16 Jan 2020
 +
|-
 +
| Wiki page creation || 16 Jan 2020
 
|-
 
|-
 
| Read GPS data with Pandas || 20 Jan 2020
 
| Read GPS data with Pandas || 20 Jan 2020
Line 55: Line 57:
 
|-
 
|-
 
| Supervisor meeting 2 || 30 Jan 2020
 
| Supervisor meeting 2 || 30 Jan 2020
 +
|-
 +
| Manually analyze user profile data || 1 Feb 2020
 +
|-
 +
| Designed code to automatically analyze user profile data || 2 Feb 2020
 +
|-
 +
| Finish analysis of Block 10 user profile data || 3 Feb 2020
 +
|-
 +
| Sponsor meeting 3 || 4 Feb 2020
 +
|-
 +
| Supervisor meeting 3 || 6 Feb 2020
 +
|-
 +
| Sponsor meeting 4 || 11 Feb 2020
 +
|-
 +
| Midterm Presentation || 20 Feb 2020
 +
|-
 +
| Route Analysis || 3 Mar 2020
 +
|-
 +
| Supervisor meeting 4 || 5 Mar 2020
 +
|-
 +
| Route Analysis - Testing|| 10 Mar 2020
 
|}
 
|}

Latest revision as of 17:43, 15 March 2020

WheelGologo.png

HOME

BACKGROUND

PROJECT OVERVIEW

PROJECT MANAGEMENT

DOCUMENTATION

Milestones

Number Milestone Planned Start Date Planned End Date Status Mitigation Plan
1 Finalization of topic 20 Dec 2019 3 Jan 2020 Completed
2 Completion of cleaning data 4 Jan 2020 31 Jan 2020 Completed
3 Data Analysis 1 Feb 2020 30 Mar 2020 In Progress (New) User Profile Analysis
4 Report Finished 1 April 2020 30 Apr 2020 In Progress

Project Schedule

Activity Date
Sponsor meeting 1 15 Jan 2020
Supervisor meeting 1 16 Jan 2020
Wiki page creation 16 Jan 2020
Read GPS data with Pandas 20 Jan 2020
Combine data for each user 27 Jan 2020
Statistical analysis on GPS data 27 Jan 2020
Sponsor meeting 2 29 Jan 2020
Supervisor meeting 2 30 Jan 2020
Manually analyze user profile data 1 Feb 2020
Designed code to automatically analyze user profile data 2 Feb 2020
Finish analysis of Block 10 user profile data 3 Feb 2020
Sponsor meeting 3 4 Feb 2020
Supervisor meeting 3 6 Feb 2020
Sponsor meeting 4 11 Feb 2020
Midterm Presentation 20 Feb 2020
Route Analysis 3 Mar 2020
Supervisor meeting 4 5 Mar 2020
Route Analysis - Testing 10 Mar 2020