List of requirement changes | Added in tertiary functionality (Exercise Recommendation) - To further enhance the Indicate Injury feature, we enable our users to save time in finding a suitable workout without hindering their workout routine despite their injury |
Project Achievement | Description |
---|---|
Unique Feature | Proposed and developed the Indicate Injury feature for RunKicker app, in which is unique and not yet out in the market. |
Teamwork | Able to successfully complete an Android app and a Web Portal Management System with a 4 man group. |
Platform | Modules | Total Functions | Completed Functions | Remaining Functions | Status | Confident Level (0-1) | Comment | % Total Done |
---|---|---|---|---|---|---|---|---|
Mobile Application | Account | 4 | 4 | 0 | 100% | 1 | Fully deployed and tested | 100% |
Food | 3 | 3 | 0 | 100% | 1 | Fully deployed and tested | ||
Activity | 7 | 7 | 0 | 100% | 1 | Fully deployed and tested | ||
Event | 4 | 4 | 0 | 100% | 1 | Fully deployed and tested | ||
Affective | 1 | 1 | 0 | 100% | 1 | Fully deployed and tested | ||
Social | 2 | 2 | 0 | 100% | 1 | Fully deployed and tested | ||
Analytical | 2 | 2 | 0 | 100% | 1 | Fully deployed and tested | ||
Friends | 2 | 2 | 0 | 100% | 1 | Fully deployed and tested | ||
Notifications | 2 | 2 | 0 | 100% | 1 | Fully deployed and tested | ||
Web Application | Management | 4 | 4 | 0 | 100% | 1 | Fully deployed and tested. Sean will be implementing the front-end, Guan Ze will be implementing the back-end. | 100% |
Iterations | Planned | Actual | Comments | ||
---|---|---|---|---|---|
1 | Account Module | 23 May 2018 | 24 May 2018 | Sean and Guan Ze went for OCSP so team was short of manpower. Delayed for 1 day. | |
2 | Food Module | 12 June 2018 | 12 June 2018 | Everything went as plan | |
3 | Activity Module | 1 July 2018 | 1 July 2018 | One of the hardest and most complicated module in this entire project. Everyone worked hard and the team managed to complete the iteration within the timeframe. | |
4 | Events Module | 18 July 2018 | 18 July 2018 | Everything went as plan | |
5 | Regression Testing | 28 July 2018 | 28 July 2018 | Everything went as plan | |
User Acceptance Testing 1 | 3 August 2018 | 3 August 2018 | Everything went as plan. Had 30 participants participated in the user testing | ||
6 | Acceptance | 17 August 2018 | 17 August 2018 | Completed our Acceptance milestone. | |
7 | Friends Module | 22 August 2018 | 22 August 2018 | A interesting module that we are excited about. Allowing us to add friends. | |
Notifications Module | 25 August 2018 | 25 August 2018 | One of the hardest module due to the different scenarios that user might face. Everything went as plan. | ||
8 | Analytical Module | 4 September 2018 | 4 September 2018 | Everything went as plan | |
Social Module | 7 September 2018 | 7 September 2018 | Everything went as plan | ||
9 | Regression Testing | 21 September 2018 | 21 September 2018 | Solved some bugs that were not found in previous iterations. | |
User Acceptance Testing 2 | 25 September 2018 | 25 September 2018 | Everything went as plan. Had 30 participants participated in the user testing (12x Unfit and Unmotivated, 13x Overweight, 5x Obese) | ||
10 | Affective Module | 2 October 2018 | 2 October 2018 | Completed and tested. | |
Mid Term | 4 October 2018 | 4 October 2018 | Completed. | ||
Account Module (Tertiary Function - Choose between 2 personality types) | 5 October 2018 | 5 October 2018 | Completed and tested. This function in the Account Module allow user to choose between 2 personality types | ||
11 | Food Module | 17 October 2018 | Drop tertiary module as discussed with team members and sponsors. | ||
Management Module | 25 October 2018 | Completed and tested. | |||
Event Module (Tertiary Function - Calendar feature) | 19 October 2018 | 19 October 2018 | Completed and tested. | ||
Activity Module (Tertiary Function - Recommend Workout) | 25 October 2018 | Added new activity tertiary module to enhance the indicate injury feature. Completed and tested. | |||
12 | Friends Module | 4 November 2018 | Drop tertiary module as discussed with team members and sponsors. | ||
Poster Submission | 29 October 2018 | 29 October 2018 | Poster is submitted successfully | ||
Management Module | 2 November 2018 | Completed and tested. | |||
13 | Final Day | 26 November 2018 | |||
Client Handover | 27 November 2018 | ||||
Poster Day | 2 December 2018 |
Risk | Probability | Impact | Mitigation |
---|---|---|---|
Scope Creep. The Runkicker WMS module may experience changes and addition of unnecessary features. | Low | High | The team must ensure that the specific requirements of this module and its functionalities/features are discussed with the sponsors. Both parties's visions have to be aligned to the fact that the WMS will only showcase features/functionalities that are necessary. |
Tertiary function of the Runkicker app, which is the scheduling of an event on Google Calendar, may be complicated and the team might not have sufficient time to implement. | Low | High | The team has to perform early adequate research and review online tutorials and Google APIs on how to connect the current "Event Creation" function in the app with the phone's Google Calendar. |
Where | Why |
---|---|
AWS Server Configuration | Commands and knowledge of knowing how to deploy API endpoints onto the Server |
MySQL Database Table Structuring | Friends Module - structuring the database to store user’s friend list and pending friend list |
Mobile App | Notification Module - leveraging on Google FCM (Firebase Cloud Messaging) service to send push notification to devices |
Stage | Specification | Modules |
---|---|---|
Project Management | Meeting Minutes | TheBrosCode MeetingMinutes |
Task Metrics | TheBrosCode Metrics | |
Bug Metrics | TheBrosCode BugMetric | |
Analysis | Use Case Diagram | TheBrosCode Documentation |
Design | ER Diagram | TheBrosCode ERDiagram |
Testing | UAT 3 | TheBrosCode UAT |
Presentation Slides | Final | TheBrosCode UAT |
UAT | Category |
---|---|
2 | Overall User Testing Results Summary |
2 | Sponsors Test Summary |
2 | Users Test Summary |
3 | Post Test Questionnaire |
3 | Task Instructions |
Member | Learning Outcome |
---|---|
Tommy | Able to manage the scope, cost, timing, and quality of the project, at all times focused on project success as defined by project stakeholders. To be able to discuss and take into use more front-end technologies |
Chun Ming | Gain real-life experience by putting my coding abilities to a test by working on such mobile apps Building teamwork spirit and balanced work allocation are essential to a project's progress Communication and management abilities are integral factors to a project's success |
Sean Hoon | Improve communication skills to create the right end product Cultivate a good understanding on web UX/UI to ensure a good user experience Hopes to deepen my understanding on front-end web development |
Tan Guan Ze | Hopes to explore and develop automated test scripts Be more precise and assure quality in all the work done Explore the capabilities of android programming and the extent of its functions |