== Schedule Metric (Midterm) == | == Schedule Metric (Midterm) == | ||
+ | |||
+ | We use '''Overtime %''' for '''Schedule Metric'''. We calculate our overtime % by subtracting "actual time" from "planned time", and then, divide the result by "plan time" and multiply it with 100%. Actual time is the time duration we took to finish the functions within an iteration ,and planned time is the time duration we had planned to finish the functions within an iteration. | ||
+ | |||
'''Graph'''<br> | '''Graph'''<br> | ||
[[Image:EnableSchMetric.jpg|Schedule Metric]] <br><br> | [[Image:EnableSchMetric.jpg|Schedule Metric]] <br><br> |
Revision as of 19:50, 27 November 2010
Contents
Schedule Metric (Midterm)
We use Overtime % for Schedule Metric. We calculate our overtime % by subtracting "actual time" from "planned time", and then, divide the result by "plan time" and multiply it with 100%. Actual time is the time duration we took to finish the functions within an iteration ,and planned time is the time duration we had planned to finish the functions within an iteration.