IS480 Team wiki: 2017T1 PlusMinus TestResults
Jump to navigation
Jump to search

![]() |
![]() |
![]() |
![]() |
![]() |
Persona Scenario | Diagrams | Test Results |
Meeting Minutes | Presentation |
User Test 1 - Sprint 6 [COMPLETED]
Date of UT: | 10 August 2017 |
Time of UT: | 1.30pm - 3.30pm |
Location: | Ang Mo Kio Thye Hua Kwan Hospital |
# of Users: | 4 |
Roles Assigned: | Super User (2), Course Creator (1), HR Admin (1) |
Objectives: |
1. To ensure that the portal is aligned with the requirements of the client |
2. To receive feedback from client |
Scope: |
1. Login |
2. eLearn - Courses |
2. AI ChatBot |
Documents: | |
- Download User Test Case: | UT 1 Script |
- Download Feedback Form: | UT 1 Feedback |
- Download User Test Slides: | UT 1 PPT |
- Access to Issues Log: | Issue Log Google Sheet |
- Download UT Results: | UT 1 Results |
- Download Meeting Minutes: | UT 1 Meeting Minutes |
User Test 2 - Sprint 9 [COMPLETED]
Date of UT: | 20 September 2017 |
Time: | 3.30pm to 6.30pm |
Location: | Ang Mo Kio Thye Hua Kwan Hospital |
# of Users: | 4 |
Roles Assigned: | Super User (2), Course Creator (1), HR Admin (1) |
Objectives: |
1. To ensure that the newer functions developed is aligned with the requirements of the client |
2. To receive feedback from client |
3. To update client on team's progress |
Scope: |
1. Login |
2. eLearn - Courses |
3. AI ChatBot |
4. eLearn - Quiz |
5. Account Settings |
6. User Management |
Documents: | |
- Download User Test Case: | UT 2 Script |
- Download Feedback Form: | UT 2 Feedback |
- Download User Test Slides: | UT 2 PPT |
- Access to Issues Log: | Issue Log Google Sheet |
- Download UT Results: | UT 2 Results |
- Download Meeting Minutes: | UT 2 Meeting Minutes |
User Acceptance Test (UAT) - Sprint 13 [COMPLETED]
Date: | 08 November 2017 |
Time: | 3pm to 5pm |
Location: | Ang Mo Kio Thye Hwa Kuan Hospital |
# of Users: | 10 |
Objectives: |
1. To ensure that all functions developed is aligned with the requirements of the client |
2. To ensure that all bugs are found |
3. To prepare for Handover/Sign-off |
Scope: |
1. eLearn (Course, Quiz, Learning Materials) |
2.AI Chatbot |
3. Account Settings |
4. Resources/Content |
5. User Management |
Documents: | |
- Download User Acceptance Test Cases: | UAT Script |
- Download Feedback Form: | UAT Feedback |
- Download User Acceptance Test Slides: | UAT PPT |
- Access to Issues Log: | Issue Log Google Sheet |
- Download UT Results: | UAT Results |
- Download Meeting Minutes: | UAT Meeting Minutes |
Individual Sprint's Test Case
Test Plan: Download Test Plan
Sprint | Date | Test Case |
---|---|---|
User Test 1 - Unexecuted
Reasons to failure of UT Execution:
Meeting was used to discuss about the change in project scope.
Date: | 27 Jun 2017 |
Time: | 7.30pm |
Location: | SIS Meeting Room 4-1 |
# of Users: | 4 |
Objectives: |
1. Gather feedback on portal colour scheme and design |
2. Check on the logic of Individual Approval Route Workflow |
Scope: |
1. Login |
2. Individual Approval Workflow |
3. Application of courses |
4. Approval |
You can download User Test Case here: User Test 1 |
You can download Feedback Survey Form here: Feedback UT 1 |