IS480 Team wiki: 2016T2 LOCK Project Metrics
Revision as of 23:05, 12 January 2016 by Danielyeong.2013 (talk | contribs)
HOME | ABOUT US | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION |
Contents
Schedule Tracking Category
Score(%) | Mitigation Action |
---|---|
SM < 50 | Very Late |
50 < SM <= 90 | Slightly Late |
90 < SM <= 110 | On Time |
110 < SM <= 150 | Slightly Early |
150 < SM | Too Early |
SM Score = Estimated No. of Days in Iteration / Actual No. of Days spent in Iteration
Score(%) | Mitigation Action |
---|---|
SM < 50 | Immediately inform Supervisor Ben Gan and client about the slip within 24 hours. Using the same action for 50 < SM <= 90, consider dropping functionalities. |
50 < SM <= 90 | PM to discuss with team and re-estimate for future iterations. Eat into buffer days if any change is needed. Analyze the cause of delay and make necessary corrections. |
90 < SM <= 110 | Estimates are fairy accurate and we are roughly on track. Consider adding remaining days into buffer date or deducting buffer days to cater for changes. |
110 < SM <= 150 | Over estimated the effort required. Re-estimate the tasks for future iterations and add number of days to buffer days. |
150 < SM | Immediately inform Supervisor Ben Gan and client about the slip within 24 hours. Using the same action for 110 < SM <= 150, consider adding functionalities. |
Impact Score
Severity | Description |
---|---|
Low Impact (1 - 4 points) | Inconsequential. Simple typo error or minor user interface misalignment. |
High Impact (5 - 9 points) | The system runs. However, some non-critical functionalities are not working |
Critical Impact (10 points) | The system is down or is unstable after a short period of time. Bug fix immediately to continue |
Mitigation Plan
Total Score = # Bugs (Low) x 1 + # Bugs (High) x 5 + # Bugs (Critical) x 10
Bug Score | Mitigation Action |
---|---|
Score <= 10 | Use buffer time to fix. |
10 < Score <= 20 | Use planned debugging time in the iteration to carry out bug fix |
Score > 20 | Stop current development and resolve the bug immediately. Project Manager to reschedule the project. |