Metrics
|
Task Metric (TM)
TM SCORE = ACTUAL No. of Tasks Completed in Iteration / PLANNED No. of Tasks in Iteration
Score (%) | Action |
---|---|
< 50 | 1. Immediately, inform your supervisor about the slip within 24 hours. 2. Then use the same mitigation as the category 50 < TM < 90 and seriously consider dropping tasks. |
50 < TM <= 90 | 1. Re-estimate the tasks for the future iterations. 2. Deduct the number of days behind schedule from buffer days. |
90 < TM <= 110 | Our estimates are fairly accurate, and we are roughly on track. 1. Add/Deduct the number of days behind schedule from buffer days. |
110 < TM <= 150 | Gross over-estimated the effort required. 1. Re-estimate the tasks for the future iterations. |
150 < TM | 1. Immediately, inform your supervisor about the slip within 24 hours. 2. Then use the same mitigation as the category 110 < TM < 150 |
Bug Metric
FORMULA = 1 x No. of LOW + 5 x No. of HIGH + 10 x No. of CRITICAL
Severity | Desrcription |
---|---|
LOW Impact (1 points) | Unimportant. Typo error or small User Interface (UI) alignment issues. |
HIGH Impact (5 points) | The system runs. However, some non-critical functionalities are not working. |
CRITICAL Impact(10 points) | The system is down or is un-usable after a short period of time. We have to fix the bugs to continue. |