2 |
7 |
Use planned debugging time |
3 |
7 |
Use planned debugging time |
4 |
13 |
Use planned debugging time |
5 |
34 |
User Test 2 was withheld until all the bugs were solved. Future iterations have been rescheduled |
6 |
21 |
Development was stopped to resolve all bugs found. Schedule was modified for future iterations due to the extra days spent to resolve the bugs. |
7 |
18 |
Development was stopped to resolve all bugs found. Schedule was modified for future iterations due to the extra days spent to resolve the bugs. |
8 |
6 |
Use planned debugging time |
9 |
6 |
Use planned debugging time |