Schedule Metrics


Vulcan schedule metrics.PNG
Summary of Schedule Metrics
Iteration Planned Duration (Days) Actual Duration (Days) Schedule Metric Score Action Status
1 18 18 100% Estimates are generally accurate and on track. No action to be taken. Completed
2 18 32 56.25% Team is behind schedule. This is due to the complexity of the tasks planned.

Follow up action: Rescheduled the future iterations, deducted days from buffer days.

Completed
3 10 10 100% Estimates are generally accurate and on track. No action to be taken. Completed

}