Schedule Metrics
Summary of Schedule Metrics
Iteration | Planned Duration (Days) | Actual Duration (Days) | Schedule Metric Score | Action | Status | |
---|---|---|---|---|---|---|
1 | 18 | 18 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed | |
2 | 18 | 32 | 56.25% | Team is behind schedule. This is due to the complexity of the tasks planned. Follow up action: Rescheduled the future iterations, deducted days from buffer days. |
Completed | |
3 | 10 | 10 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed