Line 1,333: |
Line 1,333: |
| | | |
| ===Bug Metrics=== | | ===Bug Metrics=== |
| + | <center> |
| {|class="wikitable" width="65%" | | {|class="wikitable" width="65%" |
| ! Severity || Description | | ! Severity || Description |
Line 1,362: |
Line 1,363: |
| | Stop current development and resolve the bug immediately. Project Manager reschedules the project. | | | Stop current development and resolve the bug immediately. Project Manager reschedules the project. |
| |} | | |} |
| + | </center> |
Revision as of 16:43, 23 September 2014
Our Team
Time Line
The time line shows the IS480 milestones and the iterations for the whole project. Lining the schedule, are the functions that will be released with each deployment. The functions in the later iterations will be added to the functions already available from previous iterations.
C.R.U.D. refers to Create, Read, Update, Delete.
Schedule
|
Planned
|
Iter |
Tasks |
Milestone |
Start |
End
|
1
|
Preparation
- Documentation & Requirement Gathering
- Research on Technologies
- Setup necessary software
- Develop project proposal
Project Management
- Team roles & management
- Project Schedule
- Risk Assessment
- Learning Outcome
Technical Requirements
- Develop Use Case Diagram
- Draft database entity
|
|
23 May 2014
|
12 Jun 2014
|
2
|
Management & Documentation
- Finalise project proposal
- Prepare project writeup on wiki
- Refine UCD
- Develop diagrams
Coding Tasks
- Develop mock UI & framework
- Build up database
- Login & authentication
- Grant user roles
- Create claims
- Edit/ update claims
- Delete claims
- View claims
- Save function for unsubmitted claims
Testing
- Develop test cases for revelant functions
- Integration testing
- Debugging
Documentation
- Update revelant documents & progress
- Update wiki page & project progress
|
Proposal 18 Jun 2014
|
13 Jun 2014
|
26 Jun 2014
|
3
|
Coding Tasks
- Refine UI and develop UI for relevant functions
- Code for club application
- Code for acceptance and rejection of club application
- Code for removal of club application
- Code for editing of claims to relevant parties
- Code for submission of claims to relevant parties
- Code for viewing/ editting of all accounts for SMUSA Fin sec
- Code for viewing/ editting of accounts for users of different
Testing
- Develop test cases for revelant functions
- Integration testing
- Debugging
Management & Documentation
- Update wiki page & project progress
- Update database & diagrams
Deployment
|
Users |
Claims |
Accounts |
Budgeting |
Additional features
|
Create, Read, Update, Delete (C.R.U.D.)
Login
Grant user roles
Club Application
Create application
Acceptance & Reject
Remove
|
C.R.U.D.
View claims
Save unsubmitted claims
Editing of claims
Claims submission
|
R.U.
View accounts
|
|
|
|
|
27 Jun 2014
|
10 Jul 2014
|
4
|
Management
- Revise documentations / wiki page
- Revise diagrams & test cases
Coding Tasks
- Refine UI and develop UI for relevant functions
- Code for approval of claims
- Code for rejection of claims
- Code for resubmission of rejected claims
- Code for reject claims due to error
- Code for change of claims status
- Code for propose budget (save function for individual account)
- Code for edit/update of budget
- Code for removal of budget
- Code for submit budget
- Code to view budget
Testing
- Develop test cases for revelant functions
- Integration testing
- Debugging
Documentation
- Update wiki page & project progress
Deployment
|
Users |
Claims |
Accounts |
Budgeting |
Additional features
|
C.R.U.D.
Login
Grant user roles
Club Application
Create application
Acceptance & Reject
Remove
|
C.R.U.D.
View claims
Save unsubmitted claims
Editing of claims
Claims submission
Approval & Rejection
Resubmission
Status changed
|
R.U.
View accounts
|
C.R.U.D.
View budget
Save & Submit
|
|
|
|
11 Jul 2014
|
31 Jul 2014
|
5
|
Management
- Revise documentations / wiki page
- Prepare for acceptance presentation
- Revise diagrams & test cases
Coding Tasks
- Refine UI and develop UI for relevant functions
- Code for SMUSA CBD & SMUSA fin sec to edit submitted
- Code for SMUSA fin sec to allocate funds (from SAC account to every clubs' expenditure account)
- Code for deposit revenue into expenditure account (CBD fin sec & SMUSA sec)
- Code for inject funds from SAC reserve
- Code for viewing of SAC account
Testing
- Develop test cases for revelant functions
- Deploy a Minimum Viable Product (MVP)
- Integration testing
- Debugging
Documentation
- Update revelant documents & progress
- Update wiki page & project progress
Deployment
|
Users |
Claims |
Accounts |
Budgeting |
Additional features
|
C.R.U.D.
Login
Grant user roles
Club Application
Create application
Acceptance & Reject
Remove
|
C.R.U.D.
View claims
Save unsubmitted claims
Editing of claims
Claims submission
Approval & Rejection
Resubmission
Status changed
|
R.U.
View accounts
Revenue deposit
SAC - Fund allocation
SAC - Injecting funds
SAC - View accounts
|
C.R.U.D.
Submission
View budget
Save & Submit
Edit submitted budget
|
|
|
Acceptance Presentation 14 Aug 2014
|
1 Aug 2014
|
14 Aug 2014
|
6
|
Management
- Revise documentations / wiki page
- Prepare for acceptance presentation
- Revise diagrams & test cases
Coding Tasks
- Refine UI and develop UI for relevant functions
- Code for pull back funds from SAC reserve
- Code for editalble pull back formula for SMUSA fin sec
- Code for viewing of reserve account
- Code for SMUSA fin sec to approve reserve withdrawal
- Code for request reserve withdrawal (CBD & Club fin sec)
Testing
- Develop test cases for revelant functions
- Deploy MVP
- Integration Testing
- Debugging
- UAT - Iteration 5 deployment
Documentation
- Update revelant documents & progress
- Update wiki page & project progress
Deployment
|
Users |
Claims |
Accounts |
Budgeting |
Additional features
|
C.R.U.D.
Login
Grant user roles
Club Application
Create application
Acceptance & Reject
Remove
|
C.R.U.D.
View claims
Save unsubmitted claims
Editing of claims
Claims submission
Approval & Rejection
Resubmission
Status changed
|
R.U.
View accounts
Change reserve limit
Edit pullback formula
View reserve accounts
Request reserve withdrawal
Approve reserve withdrawal
SAC - Fund allocation
SAC - Injecting funds
SAC - Revenue deposit
SAC - View accounts
SAC - Pullback funds
|
C.R.U.D.
View budget
Save & Submit
Edit submitted budget
|
|
|
Initial Rollout 25 Aug 2014
|
15 Aug 2014
|
28 Aug 2014
|
7
|
Management
- Revise documentations / wiki page
- Revise diagrams & test cases
Coding Tasks
- Refine UI and develop UI for relevant functions
- Code for fund transfer between CBD & Club fin sec
- Code for report generation for fund transactions
- Code for report generation of transaction of pullback and allocation
Testing
- Develop test cases for revelant functions
- Deploy MVP
- Integration Testing
- Debugging
- UAT - Iteration 6 deployment
Documentation
- Update revelant documents & progress
- Update wiki page & project progress
Deployment
|
Users |
Claims |
Accounts |
Budgeting |
Additional features
|
C.R.U.D.
Login
Grant user roles
Club Application
Create application
Acceptance & Reject
Remove
|
C.R.U.D.
View claims
Save unsubmitted claims
Editing of claims
Claims submission
Approval & Rejection
Resubmission
Status changed
|
R.U.
View accounts
Change reserve limit
Edit pullback formula
View reserve accounts
Request reserve withdrawal
Approve reserve withdrawal
Fund transfer
SAC - Fund allocation
SAC - Injecting funds
SAC - Revenue deposit
SAC - View accounts
SAC - Pullback funds
Reports
Fund transactions
Transaction of pullback and allocation
|
C.R.U.D.
View budget
Save & Submit
Edit submitted budget
|
|
|
|
29 Aug 2014
|
11 Sep 2014
|
8
|
Management
- Revise documentations / wiki page
- Revise diagrams & test cases
Coding Tasks
- Refine UI and develop UI for relevant functions
- Code for club level report
- Code for CBD level report
- Code for SMUSA level report
- Code for report generation of transaction history
- Code for analytics dashboard
- Code for e-receipt generation
- Code for e-payment function
Testing
- Develop test cases for revelant functions
- Deploy MVP
- Integration Testing
- Debugging
- UAT - Iteration 7 deployment
Documentation
- Update revelant documents & progress
- Update wiki page & project progress
Deployment
|
Users |
Claims |
Accounts |
Budgeting |
Additional features
|
C.R.U.D.
Login
Grant user roles
Club Application
Create application
Acceptance & Reject
Remove
|
C.R.U.D.
View claims
Save unsubmitted claims
Editing of claims
Claims submission
Approval & Rejection
Resubmission
Status changed
|
R.U.
View accounts
Change reserve limit
Edit pullback formula
View reserve accounts
Request reserve withdrawal
Approve reserve withdrawal
Fund transfer
SAC - Fund allocation
SAC - Injecting funds
SAC - Revenue deposit
SAC - View accounts
SAC - Pullback funds
Reports
Fund transactions
Transaction of pullback and allocation
Club level
CBD level
SMUSA level
Transaction history
|
C.R.U.D.
View budget
Save & Submit
Edit submitted budget
|
Club level E-receipt & E-payment
Club level Analytics dashboard
|
|
|
12 Sep 2014
|
25 Sep 2014
|
9
|
Mid term preparation
Management
- Revise documentations / wiki page
- Revise diagrams & test cases
Coding Tasks
- Refine UI and develop UI for relevant functions
- Code for club level report
- Code for CBD level report
- Code for SMUSA level report
- Code for report generation of transaction history
- Code for analytics dashboard
- Code for e-receipt generation
- Code for e-payment function
- Code for vendor recommendation
Testing
- Develop test cases for revelant functions
- Deploy MVP
- Integration Testing
- Debugging
- UAT - Iteration 8 deployment
Documentation
- Update revelant documents & progress
- Update wiki page & project progress
Deployment
|
Users |
Claims |
Accounts |
Budgeting |
Additional features
|
C.R.U.D.
Login
Grant user roles
Club Application
Create application
Acceptance & Reject
Remove
|
C.R.U.D.
View claims
Save unsubmitted claims
Editing of claims
Claims submission
Approval & Rejection
Resubmission
Status changed
|
R.U.
View accounts
Change reserve limit
Edit pullback formula
View reserve accounts
Request reserve withdrawal
Approve reserve withdrawal
Fund transfer
SAC - Fund allocation
SAC - Injecting funds
SAC - Revenue deposit
SAC - View accounts
SAC - Pullback funds
Reports
Fund transactions
Transaction of pullback and allocation
Club level
CBD level
SMUSA level
Transaction history
|
C.R.U.D.
View budget
Save & Submit
Edit submitted budget
|
E-receipt & E-payment
Analytics dashboard
Vendor recommendation
|
|
Mid Term Presentation 10 Oct 2014
|
26 Sep 2014
|
10 Oct 2014
|
10
|
Management
- Revise documentations / wiki page
- Revise diagrams & test cases
Coding Tasks
- Refine UI and develop UI for relevant functions
- Code for analytics dashboard
- Code for e-receipt generation
- Code for e-payment function
- Code for vendor recommendation
Testing
- Develop test cases for revelant functions
- Deploy MVP
- Integration Testing
- Debugging
- UAT - Iteration 9 deployment
Documentation
- Update revelant documents & progress
- Update wiki page & project progress
Deployment
|
Users |
Claims |
Accounts |
Budgeting |
Additional features
|
C.R.U.D.
Login
Grant user roles
Club Application
Create application
Acceptance & Reject
Remove
|
C.R.U.D.
View claims
Save unsubmitted claims
Editing of claims
Claims submission
Approval & Rejection
Resubmission
Status changed
|
R.U.
View accounts
Change reserve limit
Edit pullback formula
View reserve accounts
Request reserve withdrawal
Approve reserve withdrawal
Fund transfer
SAC - Fund allocation
SAC - Injecting funds
SAC - Revenue deposit
SAC - View accounts
SAC - Pullback funds
Reports
Fund transactions
Transaction of pullback and allocation
Club level
CBD level
SMUSA level
Transaction history
|
C.R.U.D.
View budget
Save & Submit
Edit submitted budget
|
E-receipt & E-payment
Analytics dashboard
Vendor recommendation
|
|
|
11 Oct 2014
|
23 Oct 2014
|
11
|
Management
- Revise documentations / wiki page
- Revise diagrams & test cases
Coding Tasks
- Refine UI and develop UI for relevant functions
- Code for concurrency control
Testing
- Develop test cases for revelant functions
- Deploy fully functioning system
- Integration Testing
- Debugging
- UAT - Iteration 10 deployment
Documentation
- Update revelant documents & progress
- Update wiki page & project progress
Deployment
|
Users |
Claims |
Accounts |
Budgeting |
Additional features
|
C.R.U.D.
Login
Grant user roles
Club Application
Create application
Acceptance & Reject
Remove
|
C.R.U.D.
View claims
Save unsubmitted claims
Editing of claims
Claims submission
Approval & Rejection
Resubmission
Status changed
|
R.U.
View accounts
Change reserve limit
Edit pullback formula
View reserve accounts
Request reserve withdrawal
Approve reserve withdrawal
Fund transfer
SAC - Fund allocation
SAC - Injecting funds
SAC - Revenue deposit
SAC - View accounts
SAC - Pullback funds
Reports
Fund transactions
Transaction of pullback and allocation
Club level
CBD level
SMUSA level
Transaction history
|
C.R.U.D.
View budget
Save & Submit
Edit submitted budget
|
E-receipt & E-payment
Analytics dashboard
Vendor recommendation
|
|
UAT 27 Oct 2014
|
24 Oct 2014
|
6 Nov 2014
|
12
|
Prepare for Poster Day
Management
- Revise documentations / wiki page
- Revise diagrams & test cases
Coding Tasks
- Refine UI and develop UI for relevant functions
Testing
- Develop test cases for revelant functions
- Deploy fully functioning system
- Integration Testing
- Debugging
- UAT - Iteration 11 deployment
Documentation
- Update revelant documents & progress
- Update wiki page & project progress
Deployment
|
Users |
Claims |
Accounts |
Budgeting |
Additional features
|
C.R.U.D.
Login
Grant user roles
Club Application
Create application
Acceptance & Reject
Remove
|
C.R.U.D.
View claims
Save unsubmitted claims
Editing of claims
Claims submission
Approval & Rejection
Resubmission
Status changed
|
R.U.
View accounts
Change reserve limit
Edit pullback formula
View reserve accounts
Request reserve withdrawal
Approve reserve withdrawal
Fund transfer
SAC - Fund allocation
SAC - Injecting funds
SAC - Revenue deposit
SAC - View accounts
SAC - Pullback funds
Reports
Fund transactions
Transaction of pullback and allocation
Club level
CBD level
SMUSA level
Transaction history
|
C.R.U.D.
View budget
Save & Submit
Edit submitted budget
|
E-receipt & E-payment
Analytics dashboard
Vendor recommendation
|
|
Poster Day 10 Nov 2014
|
7 Nov 2014
|
20 Nov 2014
|
13
|
Prepare for Final Presentation
Prepare for Poster Day
Management
- Revise documentations / wiki page
Testing
- UAT - Iteration 12 deployment
- Final round of testing
Final Presentation Poster Day
|
Documentation
- Update revelant documents & progress
- Update wiki page & project progress
Deployment
|
Users |
Claims |
Accounts |
Budgeting |
Additional features
|
C.R.U.D.
Login
Grant user roles
Club Application
Create application
Acceptance & Reject
Remove
|
C.R.U.D.
View claims
Save unsubmitted claims
Editing of claims
Claims submission
Approval & Rejection
Resubmission
Status changed
|
R.U.
View accounts
Change reserve limit
Edit pullback formula
View reserve accounts
Request reserve withdrawal
Approve reserve withdrawal
Fund transfer
SAC - Fund allocation
SAC - Injecting funds
SAC - Revenue deposit
SAC - View accounts
SAC - Pullback funds
Reports
Fund transactions
Transaction of pullback and allocation
Club level
CBD level
SMUSA level
Transaction history
|
C.R.U.D.
View budget
Save & Submit
Edit submitted budget
|
E-receipt & E-payment
Analytics dashboard
Vendor recommendation
|
|
Final Rollout 1 Dec 2014 Final Presentation 24 Nov - 2 Dec 2014 Poster Day 3 Dec 2014
|
21 Nov 2014
|
3 Dec 2014
|
Risks & Constraints
Risk Table
Probability
|
1-low |
2-medium |
3-high
|
Effect
|
1-low |
2-medium |
3-high
|
Priority
|
Higher number more important
|
Project Risk
|
Possible Risk |
Reason & Implications
|
Probability (1-3) |
Effects (1-3) |
Priority (P x E) |
Strategy
|
Project may not be accepted
|
Implications/Reason
Project is being done for the third time
|
Medium(2)
|
High(3)
|
6
|
Do our best to satisfy expectations of Course Coordinator.
|
Incompatibility with client’s server when application is deployed
|
Implications/Reason
Client has their own server/domain
|
Low (1)
|
High(3)
|
3
|
Project Manager to search for plausible solutions.
Lead Developer to explore deploying on other servers in case compatibility issues cannot be resolved.
|
Underestimation of scope during development and testing
|
Implications/Reason
Over-confidence of development ability
|
Low (1)
|
High(3)
|
3
|
Project Manager to allocate buffer time in schedule and monitor schedule metrics closely. Scheduling of tasks to be adjusted according to metrics.
Team to seek advice from supervisor as to whether certain functionalities should be dropped.
|
Insufficient users for testing
|
Implications/Reason
Lack of incentives for users to do testing for us
|
Medium(2)
|
Medium(2)
|
4
|
Business Analyst to discuss with sponsors to provide users with incentives.
|
Inaccurate feedback given by testers
|
Implications/Reason
Wrong testing mind-set (i.e. purpose of test is to show that application works, not to find defects or testers’ lack of commitment to support the testing efforts)
|
Medium(2)
|
Medium(2)
|
4
|
Team to get non-IT users for testing to ensure that feedback is more applicable to the generic public to ensure user-friendliness.
Testers to be briefed and encouraged to test the application without reservations.
|
Team Risk
|
Possible Risk |
Reason & Implications
|
Probability (1-3) |
Effects (1-3) |
Priority (P x E) |
Strategy
|
Team is faced with technical difficulties
|
Implications/Reason
Inadequate skills
|
Medium(2)
|
High(3)
|
6
|
Lead Developer to learn these new skills and teach team.
Systems analyst to research on other methods/technologies that could provide an easier solution.
|
Team member is faced with sudden illness
|
Implications/Reason
Virus attack
|
High(3)
|
High(3)
|
9
|
Project Manager to reschedule tasks or reallocate tasks to another member.
Project Manager to include buffer days in project schedule to accommodate such situations.
|
Team member drops module at the eleventh hour
|
Implications/Reason
Inability to cope
|
Low(1)
|
High(3)
|
3
|
Project Manager to reallocate tasks.
Team members to devote more time to FYP.
|
Malfunction of software/hardware during development phase
|
Implications/Reason
Software crash/hardware malfunction
|
Medium(2)
|
High(3)
|
6
|
Project Manager to reschedule tasks.
Team to consistently back up all data.
|
Sponsor Risk
|
Possible Risk |
Reason & Implications
|
Probability (1-3) |
Effects (1-3) |
Priority (P x E) |
Strategy
|
Constantly adding/changing of requirements
|
Implications/Reason
Sponsor unsure of all that they want from the very beginning
|
High(3)
|
High(3)
|
9
|
Major changes are not permitted after agreement on requirements.
Project Manager to look at schedule for minor changes to see if project can still be completed on time if changes are accommodated.
Lead Developer and Systems Analyst to accommodate changes if changes are accepted.
Business Analyst to reject if changes are not accepted.
|
Project is not taken up by SMUSA after completion
|
Implications/Reason
Users are not comfortable with the system and opt instead to revert back to their old way of doing things
|
High (3)
|
Low (1)
|
3
|
Team to organize training sessions for users.
Project Manager to assign team member to provide assistance if need be.
|
SMUSA does not know how to operate the system
|
Implications/Reason
SMUSA lacks technical knowledge
|
Medium(2)
|
Low (1)
|
2
|
Business Analyst to discuss with SMUSA on whether to add user manuals.
|
Miscommunication between Business Analyst and SMUSA
|
Implications/Reason
Language interpretation issues
|
High(3)
|
Low (1)
|
3
|
Team to discuss with supervisor before proceeding.
|
External Risk
|
Possible Risk |
Reason & Implications
|
Probability (1-3) |
Effects (1-3) |
Priority (P x E) |
Strategy
|
Application will not be used after completion
|
Implications/Reason
Users are resistant to change
|
Medium(2)
|
High(3)
|
6
|
User Champion
We have discussed with SMUSA and agreed that the current SMUSA finance secretary - Ellora, is the user champion of the system.
Current SMUSA Exco will educate the new exco about their processes using the system, old methods will not be transferred to the new exco.
Incoming batch of finance secretaries will be the UAT testers of the program.
Deployment Strategy
SMUSA secretaries will use the early deployed system in parallel with their current processes.
We will be using UATs for new finsec to familiarize themselves with system.
- Instead of deploying late, we will be deploying early (iteration 5).
- We have discussed with SMUSA, they agreed for smusa finsecs to use the system in parallel. In this way, we will get early feedback from real users.
- We have also arranged for training to be done during the Leader Symposium, a Leadership workshop for new student leaders of the student organizations.
|
No maintenance of system after completion of project
|
Implications/Reason
No appointed person to maintain system.
|
Medium(2)
|
Medium(2)
|
4
|
We have discussed with our client, and come to this arrangement with our client:
- We will have Work Study Grant (WSG) for 1 team member to maintain system for 1 year
- On the job training for people to maintain the system for subsequent years
|
Metrics
Schedule Metrics
The formula for calculating schedule metrics is as follows: Estimated time / Actual Time * 100
Score (S) tiers |
Actions to take
|
S <= 50%
|
Team's progress is TOO SLOW!!!
- Reflect on progress and reassess schedule.
- Consider dropping functions.
|
50% < S <= 90%
|
Team's progress is too slow. Tasks are possibly under-estimated.
- Consider the possibility of tasks being under-estimated.
- Use buffer days if available.
- If there are no buffer days available, consider dropping functions.
|
90% < S <= 110%
|
Estimations are fairly accurate.
|
110% < S <= 150%
|
Team's progress is too fast
- Reflect on progress and reassess schedule.
- Add number of days gained as buffer days.
|
150% < S
|
Team's progress is TOO FAST!!!
- Mitigations are the same as the previous tier.
|
Iteration |
Planned Duration |
Actual Duration |
Metric Score |
Action
|
1 |
20 |
20 |
1.00 |
Proceed as planned
|
2 |
13 |
14 |
0.93 |
Proceed as planned
|
3 |
13 |
12 |
1.08 |
Proceed as planned
|
4 |
21 |
22 |
0.95 |
Proceed as planned
|
5 |
13 |
13 |
1.00 |
Proceed as planned
|
6 |
13 |
15 |
0.87 |
Underestimated complexity of coding tasks, arrange more time for similar tasks in future iterations
|
7 |
13 |
13 |
1.00 |
Proceed as planned
|
Bug Metrics
Severity |
Description
|
Low impact (1 point)
|
Unimportant. Typo error or small user interface alignment issues.
|
High impact (5 points)
|
The system runs. However, some non-critical functionalities are not working.
|
Critical impact (10 points)
|
The system is down or is un-usable after a short period of time. We have to fix the bugs to continue.
|
Points Calculation: Total = 1 x num (low) + 5 x num (high) + 10 x num (critical)
Points in iteration (P) |
Action
|
P <= 5
|
Fix during buffer time only.
|
5 < P < 10
|
Use the planned debugging time.
|
10 <= P
|
Stop current development and resolve the bug immediately. Project Manager reschedules the project.
|