IS480 Team wiki: 2013T1 ThunderBolt Project Documentation Usability Test
About Us | Project Overview | Project Management | Project Documentation |
Diagrams | Prototype | Usability Test | Meeting Minutes | Downloads |
Internal Testing
Team perform regression testing at end of each iteration. Refer to our test plan, test case and results below.
Click here for our test plan:[1]
Click here for our test cases by iterations: [2]
Usability Test 1
Date and Venue
Date: 2 Sep 2013 |
Participants
No. of Participants: 10 |
Scope of Test
Testing Method
A list of tasks based on different scenarios were given to participants and they need to follow the scenarios and figure out how to complete them in the system.
Respective facilitators who sat beside them need to observe and record down how they were using the system to complete the task assigned. |
Test Results
When asked about what do they like about our system: What asked what they dislike about the system: Improvements they would like to have to have a better user experience: |
Documentation
Usability Test 2
Date and Venue
Date: 4 Oct 2013 |
Participants
No. of Participants: 21 |
Scope of Test
User Testing 2 has been expanded from User Testing 1 to include 5 more features, which are highlighted in yellow.
Testing Method
A list of tasks based on different scenarios were given to participants and they need to follow the scenarios and figure out how to complete them in the system.
Respective facilitators who sat beside them need to observe and record down how they were using the system to complete the task assigned. |
Test Results
Comparison of User Testing 1 survey result and User Testing 2 survey result. Overall, MORE users agree with our system!
|
Documentation
Usability Test 3
Date and Venue
Date: 18 Nov 2013 |
Participants
No. of Participants: 25 |
Scope of Test