Difference between revisions of "IS480 Team wiki: 2012T1 M.O.O.T/Project Management/Risk Management"
Jump to navigation
Jump to search
Line 1: | Line 1: | ||
<font face="century gothic" size="2"> | <font face="century gothic" size="2"> | ||
− | {| style="background-color:none; color:#ffffff; border-bottom: | + | {| style="background-color:none; color:#ffffff; border-bottom:6px solid #9400D3; border-top:6px solid #9400D3; border-left:6px solid #9400D3; border-right:6px solid #9400D3;" width="100%" cellspacing="0" cellpadding="0" valign="top" | |
| style="padding:0.3em; font-size:100%; background-color:#ffffff; text-align:center; " width="6%" | | | style="padding:0.3em; font-size:100%; background-color:#ffffff; text-align:center; " width="6%" | | ||
[[IS480_Team_wiki:_2012T1_M.O.O.T | <font color="#000000">Home</font>]] | [[IS480_Team_wiki:_2012T1_M.O.O.T | <font color="#000000">Home</font>]] |
Revision as of 10:00, 19 July 2012
Project Schedule | Methodology | Metrics | Risk Management | Minutes Repository |
Risk Management
S/N | Risk Statement | Impact | Likelihood | Impact Level | Mitigation Strategy | Status |
---|---|---|---|---|---|---|
Technology & Learning Risk | ||||||
1 | Lack of documentation for Kinect SDK |
|
High | High |
|
|
2 | No suitable gestures library that we can use |
|
High | High |
|
|
3 | Self-written motion gestures may be inaccurate/inconsistent/too difficult to perform. |
|
High | High |
|
|
4 | Team is unfamiliar with working with new technology & tools |
|
High | High |
|
|
Scope Risk | ||||||
5 | Sponsor changes his requirements frequently |
|
Medium | Medium |
|
|
6 | Team overpromising new features |
|
Medium | Medium |
|
|
Development Risk | ||||||
7 | There is a critical bug that affects the core functionalities |
|
High | High |
|
|
Schedule Risk | ||||||
8 | Team members have other commitments and different priorities |
|
Medium | High |
|