List of Meetings
Iteration | Description | Start Date | End Date | ||
---|---|---|---|---|---|
~
|
Team Forming & Project Sourcing | 08.08.11
|
31.08.11
| ||
1
|
Start of Iteration 1 | 01.09.11
|
23.10.11
| ||
Requirements Gathering | 08.08.11
|
31.08.11
| |||
Technology Research Phase | 08.08.11
|
31.08.11
| |||
Research on HTML 5 | 08.08.11
|
31.08.11
| |||
Research on phoneGap | 08.08.11
|
31.08.11
| |||
Design Phase | 08.08.11
|
31.08.11
| |||
Use-Case Diagram and Description | 08.08.11
|
31.08.11
| |||
WireFrame Design | 08.08.11
|
31.08.11
| |||
Storyboard | 08.08.11
|
31.08.11
| |||
Project Milestones | 08.08.11
|
31.08.11
| |||
Start of FYP AY11/12 Term 2 | 08.08.11
|
31.08.11
| |||
Design Review Evaluation (with Sponsors) | 08.08.11
|
31.08.11
| |||
Design Acceptance | 08.08.11
|
31.08.11
| |||
2
|
Start of Iteration 2 | 08.08.11
|
31.08.11
| ||
3
|
Start of Iteration 3 | 08.08.11
|
31.08.11
| ||
4
|
Start of Iteration 4 | 08.08.11
|
31.08.11
| ||
5
|
Start of Iteration 5 | 08.08.11
|
31.08.11
| ||
6
|
Start of Iteration 6 | 08.08.11
|
31.08.11
| ||
7
|
Start of Iteration 7 | 08.08.11
|
31.08.11
| ||
8
|
Start of Iteration 8 | 08.08.11
|
31.08.11
| ||
9
|
Start of Iteration 9 | 08.08.11
|
31.08.11
| ||
10
|
Start of Iteration 10 | 08.08.11
|
31.08.11
|