Schedule
Week No./Date | Tasks | Milestones | Minutes |
---|---|---|---|
Week 1 4/1/2016 |
Finalise our project sponsor Gather requirements |
10 Jan 2359 Proposal & Wikipedia |
Minutes 1 |
Week 2 11/1/2016 |
Obtain data Familiarize with technologies Generate base layers for the web application |
||
Week 3 18/1/2016 |
Generate base layers for the web application | Minutes 2 | |
Week 4 25/1/2016 |
Add new layers into web application | Minutes 3 | |
Week 5 1/2/2016 |
Set up search feature | Minutes 4 | |
Week 6 8/2/2016 |
Add upload files to layer feature | Client Review Session | |
Week 7 15/2/2016 |
Geocode data | Interim Report Update Wikipedia |
Minutes 6 |
Week 8 22/2/2016 |
Computation of input options | ||
Week 9 29/2/2016 |
Visualisation | ||
Week 10 7/3/2016 |
Create export results module | ||
Week 11 14/3/2016 |
Client Review Session Refine web application |
||
Week 12 21/3/2016 |
Refine web application | ||
Week 13 28/3/2016 |
Refine web application | Final Presentation & Report Update Wikipedia Poster submission |
Gantt Chart