Griffins Project Management

From Analytics Practicum
Revision as of 12:18, 23 February 2016 by Yuling.tan.2012 (talk | contribs)
Jump to navigation Jump to search
Home Project Proposal Project Management Deliverables


Schedule
Week No./Date Tasks Milestones
Week 1
4/1/2016
Finalise our project sponsor
Gather requirements
10 Jan 2359
Proposal & Wikipedia
Week 2
11/1/2016
Obtain data
Familiarize with technologies
Generate base layers for the web application
Week 3
18/1/2016
Generate base layers for the web application
Week 4
25/1/2016
Add new layers into web application
Week 5
1/2/2016
Set up search feature
Week 6
8/2/2016
Add upload files to layer feature Client Review Session
Week 7
15/2/2016
Geocode data Interim Report
Update Wikipedia
Week 8
22/2/2016
Computation of input options
Week 9
29/2/2016
Visualisation
Week 10
7/3/2016
Create export results module
Week 11
14/3/2016
Client Review Session
Refine web application
Week 12
21/3/2016
Refine web application
Week 13
28/3/2016
Refine web application Final Presentation & Report
Update Wikipedia
Poster submission
Gantt Chart

AP Team12 Griffins Gantt Chart2.JPG