ANLY482 AY2016-17 T2 Group 2 Project Management
Revision as of 22:00, 19 February 2017 by Leejia.yong.2013 (talk | contribs)
Current Progress
- Proposal wiki updated
- Proposal report updated
- Interim wiki in-progress
- Interim report in-progress
- Interim slides updated
We have finished our 4th wave of Exploratory Data Analysis (EDA). Different from the previous wave of EDA, the team looks at the general insight that can be found in all products before diving deeper into the respective product types. In this way, we will not have repetitive analysis as per those from the previous waves of EDA.
Besides that, the team is also in the midst of constructing the dashboard. We have identified the main insights from our EDA and are reviewing these insights in the form of a dashboard.
We had issues with inconsistencies and abnormalities in the datasets previously, and were bumpy in ragging and exploring the data. But we managed to solve it swiftly and did not face any delay in our schedule.
Project Schedule
Project Schedule
Tasks | Start Week | End Week | Planned Man Hours | Actual Man Hours | Team Members Involved | Status |
---|---|---|---|---|---|---|
Requirements Gathering | ||||||
Project Sponsor Confirmation | ||||||
Define Project Scope | ||||||
Data Collection | ||||||
Gather Data from Sponsor | ||||||
Project Proposal - Due on 15 January 2017 | ||||||
Proposal Preparation | ||||||
Wiki Page Preparation | ||||||
Project Preparation | ||||||
Literature Review | ||||||
Data Preparation | ||||||
Data Exploration (Dataset 1) | ||||||
Data Cleaning (Dataset 1) | ||||||
Data Transformation & Normalization (Dataset 1) | ||||||
Data Exploration (Dataset 2) | ||||||
Data Cleaning (Dataset 2) | ||||||
Data Transformation & Normalization (Dataset 2) | ||||||
Interim Practicum - Documents Due 19 February 2017 | ||||||
Report Preparation | ||||||
Wiki Update | ||||||
Presentation Preparation | ||||||
Client Review | ||||||
Interim Presentation | ||||||
Visualization | ||||||
Dashboard - Comparison of transactions before and after launch | ||||||
Dashboard - New Customers | ||||||
Insights & Recommendation | ||||||
Insights Generation | ||||||
Recommendation | ||||||
Final - Full Paper Due 2nd April 2017, Final Paper Due 26th April 2017 | ||||||
Client Review | ||||||
Report Preparation | ||||||
Wiki Update | ||||||
Presentation Preparation | ||||||
Final Paper Revision | ||||||
Conference | ||||||
Undergraduate Conference on Data Analysis |
Project Timeline
Project Timeline